Approved by Architect on 2026-07-10 (exchange commit f09c50d) with rulings C-1 (a) split, C-3 (b) Z-03 pending DHA, C-15 ASI internal QA + PE stamp. Source payload inbox/CAFI-pregenesis-trough1-baseline@1.0.0 (sim_hash sha256:ad2ab5…8f6c). Digital Triplet binding is DOCUMENTATION-DERIVED for this mechanical Frame (reactor-coupled Frames CBT-FR-REG-* will carry proper multiphysics bindings).

1. Purpose & Scope

CBT-FR-PRE-004 is the redundant secondary primary shredder Frame within the Pregenesis™ Trough 1 Line (L-TROUGH1). It contains a single equipment item — SHRD-SHR-002, a dual-shaft primary shredder rated 100 TPD nameplate at 50% duty (running paired with SHRD-SHR-001 in sibling Frame CBT-FR-PRE-001).

The Frame exists as a separate delivery unit per D-FME-01 R1 and Architect Ruling C-1 (2026-07-10, exchange commit f09c50d): the two identical redundant shredders are packaged independently to preserve independent FAT, UWP, and shipment discipline.

2. Frame Delivery Overview

Frame IDCBT-FR-PRE-004
Line (parent)L-TROUGH1
Sibling FrameCBT-FR-PRE-001 (main Trough 1 Frame)
Modules containedM-SHRD-P1 (partition)
Equipment count1 item (SHRD-SHR-002)
Shipping modeROAD-ISO-40HC single-deck
Total dry weight9,500 kg
Installed electrical160 kWe
Installed thermal0 kWth
Area classificationZ-03 combustible-dust (pending DHA per C-3)
Certifying signatoryASI internal QA + PE stamp (per C-15)
DIAG-FR-PRE-004-01 CBT-FR-PRE-004 — Frame Outline Drawing
Frame Outline
Process In
none modeled yet
CBT-FR-PRE-004
Redundant Shredder ModuleSHRD-SHR-002 · N+1 primary shredding
Process Out
none modeled yet
Auto-generated from the Frame Designer data model (Property/Building/Zone/Line/Frame/Module/Equipment schema, CBT-TB-PORTAL) — Sheet 02 canonical port layout. No Process In/Out streams or utility ports are modeled for this Frame yet; shown as-is rather than invented.

3. Line Context

Under D-FME-01 R6, CBT-FR-PRE-004 is one of two sibling Frames within Line L-TROUGH1. Two Frames deliver together (nominal): one shipment of CBT-FR-PRE-001 + one shipment of CBT-FR-PRE-004 constitute a complete Trough 1 production line. Independent shipment is permitted; independent FAT is required.

4. Module Composition

M-SHRD-P1 module is split across two Frames per Architect Ruling C-1. Each Frame carries an identical redundant shredder at 50% duty. Module identity is preserved (both shredders belong to M-SHRD-P1); the Frame-level split is a delivery discipline, not a Module reclassification.

5. Equipment Schedule

TagDescriptionDutyDry Weight (kg)Plan Area (m²)Electrical (kWe)
SHRD-SHR-002Primary Shredder B (redundant)100 TPD nameplate @ 50% duty; 160 kW9,50016160

6. Fit Check

ConstraintLimit (ROAD-ISO-40HC)ActualResult
Floor plan area29.73 m²16 m²PASS (0.54×)
Gross weight30,000 kg9,500 kgPASS (0.32×)
Height2,896 mmTBD (dual-shaft shredders typically 2.5–3.0 m)Verify at OEM selection

Height fallback: upgrade to ROAD-OPEN-SKID (3,800 mm allowance) if OEM SHRD-SHR-002 exceeds 2,896 mm.

7. Area Classification & Utilities

Area classification: Z-03 (combustible dust)

Same basis as sibling Frame CBT-FR-PRE-001 (per Architect Ruling C-3). Electrical selection Class II Div 2 minimum; Class II Div 1 in vicinity of shredder discharge.

Utility demands: 160 kWe electrical (from Zero-E PowerBlock™ via NEXUS Z1); 0 thermal / steam / N₂ / water; instrument air TBD from NEXUS Z3.

8. Frame-Boundary Interfaces

SHRD-SHR-002 is a redundant unit in parallel with SHRD-SHR-001 (in CBT-FR-PRE-001). Its Frame-boundary streams share Y-split hardware with the sibling Frame:

Stream IDFromToNotes
S-FEED-SHR-B-INCBT-FR-PRE-001CBT-FR-PRE-004Y-split from SHRD-FDR-001 discharge
S-FEED-SHR-B-OUTCBT-FR-PRE-004CBT-FR-PRE-001Shredded feed re-merges into SHRD-HMR-001 feed

9. UWP Manifest

10. FAT Plan Reference

FAT plan: TBD. Expected scope for a single-equipment Frame: weigh-in / dimensional check, SHRD-SHR-002 functional test at rated duty (100 TPD nameplate, 50% duty simulation), vibration + noise baseline, bearing temperature stabilization, sign-off by ASI QA lead + PE stamp.

Integrated commissioning test with sibling Frame CBT-FR-PRE-001 (both Frames present, feed Y-split, integrated Trough 1 operation) is a separate site-level test at OER Gate 2 — not a Frame-level FAT for either Frame.

11. Digital Triplet Binding

Provenance: DOCUMENTATION-DERIVED. Same basis as sibling Frame CBT-FR-PRE-001 §11.

12. PFMEA Hook

13. MRL Claim

Working self-assessment MRL 6–7 (identical to sibling Frame; formal assessment TBD).

14. Manufacturing Origin

Same as sibling Frame CBT-FR-PRE-001 (TBD). Ideally same ASI facility to keep tooling and QA consistent across the redundant pair.

15. Certification & QMS

ASI internal QA + PE stamp per Architect Ruling C-15.

16. Risk Register

R-401 · LOW · S:3 P:4 D:5 RPN:60

Height verification pending. Dual-shaft shredder height TBD. If OEM exceeds 2,896 mm (40HC ceiling), upgrade to ROAD-OPEN-SKID (3,800 mm). No other constraint affected.

R-402 · MEDIUM · S:5 P:7 D:4 RPN:140

Y-split feed junction ownership. The Y-split mechanical junction that routes SHRD-FDR-001 discharge to A and B shredders is a Frame-boundary component. Portal recommends: junction hardware belongs to CBT-FR-PRE-001 (as extension of the feeder), with bolted flange interface at the CBT-FR-PRE-004 inlet.

R-403 · LOW · S:3 P:5 D:4 RPN:60

Redundant vs. independent operating modes not yet defined. Nameplate is 100 TPD each at 50% duty paired. Alternative modes (100% + standby, hot swap, degraded single-unit) not defined. Defer to Trough 1 operating manual (OPS-series).

17. Assumptions & TBDs

18. Approval & Iteration Notes

Approval: Rev 0 published by Portal on 2026-07-10 concurrent with sibling Frame CBT-FR-PRE-001 (Architect approval marker f09c50d). This Frame was authored as draft v1 on the same date and inherits the C-1 / C-3 / C-15 rulings from the sibling approval.

Twin ACK: Pending Twin ACK for draft v1. Portal proceeded with publication under Architect's 'use your recommendations' delegation; Twin's ACK or rebuttal on the exchange will trigger a Rev 1 revision if needed.

Iteration items for Rev 1: Y-split ownership finalization, height verification, integrated commissioning test outcome.