Pregenesis Protocol β FMEA Register
Failure Mode & Effects Analysis Register
Modules 0A/0B/0C & Modules 1β4 | Interactive β filter by module, severity, or status
RPN Escalation Thresholds
RPN β₯ 200: Immediate engineering review β must be CLOSED before IFA release |
125β199: Action required before OER Gate 3 |
80β124: Action recommended β quarterly review |
<80: Monitored
β
Total Entries
β
RPN β₯ 200
β
RPN 125β199
β
Open Actions
β
Closed
FMEA Risk Matrix β RPN Distribution by Module
| FMEA ID | Mod | Tag | Failure Mode | System Effect | S | P | D | RPN | Current Controls | Action / Owner | Status |
|---|
CBT-PRE-FMEA-001 | Rev 0 | April 2026 | CONFIDENTIAL β CARBOTURA INC.
RPN = S Γ P Γ D | Governed by FMEA.prompt.md v1.0 | Actions tracked to named owners and OER gates
RPN = S Γ P Γ D | Governed by FMEA.prompt.md v1.0 | Actions tracked to named owners and OER gates