Pregenesis Protocol — FMEA Register

Failure Mode & Effects Analysis Register

Modules 0A/0B/0C & Modules 1–4 | Interactive — filter by module, severity, or status

Doc No.CBT-PRE-FMEA-001
RevisionRev 0
StatusActive Register
GovernanceFMEA.prompt.md v1.0
RPN Escalation Thresholds
RPN ≥ 200: Immediate engineering review — must be CLOSED before IFA release  |  125–199: Action required before OER Gate 3  |  80–124: Action recommended — quarterly review  |  <80: Monitored
Total Entries
RPN ≥ 200
RPN 125–199
Open Actions
Closed
FMEA Risk Matrix — RPN Distribution by Module
FMEA IDModTagFailure Mode System EffectSPDRPN Current ControlsAction / OwnerStatus
CBT-PRE-FMEA-001 | Rev 0 | April 2026 | CONFIDENTIAL — CARBOTURA INC.
RPN = S × P × D | Governed by FMEA.prompt.md v1.0 | Actions tracked to named owners and OER gates