Carbotura
Engineering Portal
Confidential
Central Building Services & Utilities — ICD

OmniCrude™ Bus ICD
Recyclotron™ → Regenesis Tier 2 Product Bus Interface

Product-out collection/distribution bus carrying OmniCrude™ phases OUT of the Recyclotrons™ to downstream Regenesis processing. Two-tier redundancy per D-TRAIN-01.

Doc No.CBT-ICD-OCB-001
RevisionRev 0
StatusWORKING DOCUMENT — 1st Review Draft
Date2026-07-08
ClassificationISC-2 Confidential
⚠ WORKING DOCUMENT — 1st Review Draft
Pre-Release Engineering Development. Content authored by Designer 2026-07-08 for first review. OPEN and parametric values preserved verbatim — no fill or invented values. PE sign-off not authorized. Refer to source draft designer-drafts/CBT-ICD-OCB-001_rev0_draft.md.
Direction Note
The Recyclotron Feed Header (RFH) carries prepared Manufacturing Feedstock INTO the Recyclotrons™ (PIMB→RMB). This document covers the OmniCrude™ Bus — the product-out collection/distribution bus carrying OmniCrude™ phases OUT of the Recyclotrons™ to downstream Regenesis processing. The two are distinct interfaces — do not conflate.

1. Scope & Interface Boundary

Defines the OmniCrude™ product bus interface from Recyclotron™ solids/vapor separation to the Regenesis Tier 2 downstream processing trains (2 parallel trains per 4-reactor group, 1-of-2 redundant per D-TRAIN-01).

2. OmniCrude™ Phase Register (8 canonical phases)

PhaseBus routingStatus
Gas Phase→ GPU / gas cleanupOPEN — header spec
Aromatic Condensate→ condensate handlingOPEN
Process Water Phase→ water recoveryOPEN
Carbon Phase (Vapor)→ carbon recoveryOPEN
Carbon Phase (Solid)→ solids separation (Stream B)OPEN
Metal Phase→ Regenesis MAX separationOPEN
Glass Phase→ Regenesis MAX separationOPEN
Mineral Phase→ Liquifact™ Minerals StreamOPEN

"ash" terminology is prohibited across all phase naming (firewall).

3. Interface Register

IDInterfaceParameterStatus
OCB-01Bus header diameterties to ICD-A01 (header diameter confirmation)OPEN
OCB-02Connector familyASI- flanged (confirm ID vs ASI-RFH-FLG — separate line)OPEN
OCB-03Operating T/Pparametric — OER Gate 2OPEN
OCB-04Cross-group failover manifoldsecondary redundancy tier (D-TRAIN-01)OPEN

4. Redundancy & Availability

Two-tier per D-TRAIN-01: Tier 1 in-group 1-of-2 trains; Tier 2 cross-group failover manifolds.

5. Control & Instrumentation

SCADA via ASI-DAT-MOD-TCP. Phase routing valves — OPEN tag list (ICD-A05).

6. Open Actions

7. Interface Ownership

Recyclotron™ side + downstream side: Carbotura OEM. Integration/FAT: ASI.

END OF DRAFT — CBT-ICD-OCB-001 | Rev 0 | 2026-07-08 | CONFIDENTIAL — CARBOTURA INC.
1st Review Draft · Sourced from designer-drafts/ · OPEN markers preserved