APS Module — Technical Design Specification
Atmospheric Protection System (Facility-Wide Negative-Pressure Capture & Material Recovery)
Facility-wide negative-pressure capture spanning PIMB and RMB. APS Capture Stream recovers materials as product streams via ASI-APS-FLG (8-in. flanged duct).
designer-drafts/CBT-APS-TDS-001_rev0_draft.md.
1. Executive Summary
APS is the facility-wide negative-pressure capture and material-recovery system spanning PIMB and RMB. Near-zero routine atmospheric release by design.
2. Facility Context & Module Boundaries
Captures at every ingest/transfer/processing point; ties to APS Equipment Room. Interface connector: ASI-APS-FLG (8-in. flanged duct).
3. Process Description
Continuous negative-pressure hoods → ducting → separation → recovery to product streams (carbon fines, mineral particulate). OPEN: separation train spec.
4. Feedstock Design Envelope
Capture material: MSW ejection particulate, rubber dust, H₂S, NH₃, methane, VOCs (Module 0D), mineral particulate.
5. Module Equipment Specifications
OPEN: fans, separators, filtration OEM specs (OER Gate 2).
6. APS Interface Register / Capture Points
| Tag | Point | Normal CFM | Peak CFM |
|---|---|---|---|
| DUMP-APS-HE-001 | Trough 1 head-end hood | 1,200 | 2,000 |
| DUMP-APS-HE-002 | Trough 2 head-end hood | 1,200 | 2,000 |
| LBS-VNT-001 | Module 0D tanker vent | 800 | 1,400 |
| PIMB TOTAL | ~5,100 | ~8,700 | |
7. Modular Installability & ICD
ASI-APS-FLG tie-ins; skid-bounded.
8. Utilities Register
Power (see CBT-PWR-TDS-001), controls via ASI-DAT-MOD-TCP.
9. Vendor Matrix
OPEN (OER Gate 2 OEM shortlist).
10. CAPEX Estimate
OPEN [Class 2 ±15%, 2026 USD] pending OEM quotes.
11. TIC WBS Reconciliation
OPEN.
12. Lead Time Schedule
OPEN.
13. TRL / ERL / IRL
Negative-pressure capture + cyclonic/bag separation are mature (TRL 9); integration IRL OPEN.
14. Confidence Factor
OPEN (target ≥2.85 at Rev 0).
15. Availability Model
Redundant fans, N+1 target — OPEN.
16. Risk Register
Option A callout format; S/P/D/RPN. OPEN: populate at Rev 1.
17. Spares Register
OPEN.
18. Warranty Register
ASI Unitized Warranty Passport.
Open Actions
- NFPA 652 DHA for Z-03/Z-04 (ties ICD-A04).
- Separation-train OEM selection.
1st Review Draft · Sourced from designer-drafts/ · OPEN markers preserved