Pregenesis Protocol β€” CAPEX Summary

Total Module CAPEX β€” Consolidated Summary

Pregenesis Protocol β€” All Modules | Class 2 (Β±15%) OEM Engineering Release | 2026 USD | AACE International RP 18R-97

Doc No.CBT-PRE-CAPEX-001
RevisionRev 1
AACE ClassClass 2 Β±15%
ClassificationProprietary
Currency2026 USD
AACE International RP 18R-97 β€” Class 2 (Β±15%) Estimate Basis
This capital cost estimate is classified as Class 2 (Β±15%) OEM Engineering Release per AACE International RP 18R-97. Estimating methodology: factored/parametric β€” equipment costs from budget quotes (minimum 2 OEMs per category), ROM quotes, and published industry benchmarks. Installation and indirect costs applied as percentage multipliers. Accuracy range: βˆ’15% to +15% of stated values. All values in 2026 USD.
$19M
Total Low Estimate
$37M
Total High Estimate
Β±15%
AACE Accuracy
3
Module Groups
RevCon 3
Performance Baseline
400 TPD
Factory Basis
Pregenesis Protocol CAPEX β€” Module Breakdown (Class 2 Β±15%, 2026 USD)

Consolidated CAPEX Register β€” All Pregenesis Modules

Module / Line ItemTDS ReferenceLow EstimateHigh EstimateEstimate Basis
MODULES 0A / 0B / 0C β€” Truck Intake, Dumping Floor & Trough System
TISAB building (Sprung Structure + fitout)TDS-002 Β§10$600K$1.2MSprung structure + doors + slab + fire suppression
TISAB scales + weighbridge systems (2 lanes)TDS-002 Β§10$120K$250K2Γ— NTEP-certified pit-mount scales + controllers (Mettler Toledo / Rice Lake budget quotes)
TISAB doors + controls + RFIDTDS-002 Β§10$80K$150K4 doors, PLC interlocks, RFID readers, safety systems
Dumping Floor concrete Modular Assembly + push wallsTDS-002 Β§10$800K$1.5MReinforced slab + AR400 push walls + floor drains; AACE parametric
Trough 1 + AR400 liner + wheel guidesTDS-002 Β§10$400K$800KRC walls, AR400 panels, wheel guides; structural fabricator budget quote
Trough 1 hydraulic bridges (2 pairs)TDS-002 Β§10$600K$1.2MCustom fabrication; AASHTO HL-93 rated; HPUs included; performance-spec
Trough 1 walking floors (2Γ—) + lift conveyors (2Γ—) + magnetic head pulleyTDS-002 Β§10$700K$1.4MKeith or equivalent; AR400 slats; enclosed NFPA belt; rare-earth magnet (budget quotes)
Trough 2 + 316L SS liner + leachate sump + tank + pumpsTDS-002 Β§10$500K$1.0MRC walls, 316L SS liner, sump, HDPE tank, duplex pumps; corrosion premium included
Trough 2 hydraulic bridges (2 pairs) + HPUsTDS-002 Β§10$600K$1.2MSame structure as Trough 1 bridges + 316L SS deck + Viton/PTFE seals
Trough 2 walking floors (2Γ—, 316L SS) + screw/en-masse conveyors (2Γ—)TDS-002 Β§10$550K$1.1M316L SS slats; corrosion premium ~15% vs AR400; VFD drives
EASB building + scales + all fitoutTDS-002 Β§10$700K$1.4MMirror of TISAB; 2 lanes, 4 doors, 2 scales, RFID
Thermal cameras + Li-battery detectionTDS-002 Β§10$80K$150KFixed thermal cameras at TISAB approach; SCADA integration
E&I, controls, installation labor (15% + 15%), contingency (15%)$2.84M$5.62MAACE Class 2 multipliers applied to equipment subtotal
Subtotal β€” Modules 0A/0B/0C$8.57M$16.96MClass 2 Β±15% | CBT-PRE-TDS-002
MODULES 1–4 β€” Primary Shredder Train (SHRD)
Primary Shredders (2Γ—) incl. ASI Spring IsolationTDS-003 Β§12$1.8M$3.2MBudget quotes β€” Vecoplan VEZ 3200, Lindner Polaris 2800, SSI PRI-MAX; spring isolation per ASI-ISO-SHRD-SHR-001
Hammermills (2Γ—) incl. ASI Spring IsolationTDS-003 Β§12$1.2M$2.4MBudget quotes β€” Stedman Grand Slam, Metso Lindemann LIS; spring isolation per ASI-ISO-SHRD-HMR-001
VRM Ash Pulverizers (2Γ—)TDS-003 Β§12$2.0M$3.8MBudget quotes β€” Pfeiffer MPS 2000, Loesche LM 15.2; confirmation pending grindability test (Open Action ICD-A02)
Rotational Mixer (1Γ—)TDS-003 Β§12$600K$1.2MBudget quotes β€” Readco Kurimoto, BHS-Sonthofen DKXC
Tire Pre-Shredder (1Γ—)TDS-003 Β§12$500K$900KBudget quote; standard catalog item
Magnetic Ferrous Separators (4Γ—) β€” MFS-001 through -004TDS-003 Β§12$150K$380KBudget quotes β€” Eriez, Bunting Magnetics; 4 units total
Ferrous Collection Bins (4Γ—)TDS-003 Β§12$20K$50KFabricated steel bins; 1–2 tonne capacity each; fork-liftable
Ash Storage Silos (2Γ—) + Loss-in-Weight Feeders (4Γ—) + Conveyors (7Γ—)TDS-003 Β§12$1.0M$1.8MParametric estimate; silo at 125-ton each; feeders Β±0.5% accuracy; CEMA-rated conveyors
Electrical (MCC, cabling), SCADA/Controls, Modular Assembly, Commissioning, First Fill Spares$2.6M$5.0MFactor estimates: MCC 15%; SCADA 10%; Assembly 20%; Commissioning 5%; Spares 5% of equipment
Contingency (15%)β€”$0.6MApplied per AACE Class 2
Subtotal β€” Modules 1–4$10.4M$20.1MClass 2 Β±15% | CBT-PRE-TDS-003
EXCLUDED SCOPE β€” Covered in Separate Budgets
Pregenesis main processing building (Sprung Structure)Facility civil budget$2.5M$4.5MSeparate facility civil contract; not in Pregenesis module CAPEX
APS equipment (baghouse, fans, ducts, product recovery)CBT-APS-TDS-001$1.8M$3.5MSeparate APS procurement package; referenced in each TDS APS Interface Register
Trough 2 Processing train (T2 dryer, pulverizer, dewatering)CBT-PRE-TDS-004$5.0M$15.0MModule T2; separate TDS and CAPEX package
Owner's Engineer, permits, regulatory, insuranceOwner's budget$450K$1.0MOwner cost; not in module CAPEX
Water treatment moduleFacility water treatment TDS$500K$1.5MSeparate module; receives leachate from Trough 2 and condensate from T2 dryer
TOTAL β€” Pregenesis Protocol Modules (0A/0B/0C + 1–4)$18.97M$37.06MClass 2 Β±15% | AACE 18R-97 | 2026 USD
All-in TIC (including excluded scope above)~$29.2M~$62.6MReference only β€” excluded scope at ROM accuracy; see individual TDS for detail

Cost Escalation & RevCon Return Context

MetricValueBasis
Total Pregenesis module CAPEX (mid-point)~$28MAverage of low and high estimates at Class 2 Β±15%
RevCon 3 annual revenue floor (400 TPD factory)$150M–$325M/yrRevCon 3 Valorization Ladder baseline
Simple payback β€” Pregenesis module CAPEX only<3 monthsAt RevCon 3 revenue floor; Pregenesis is intake infrastructure only β€” value creation is in Regenesis + Regenesis MAX
CAPEX per TPD capacity (Pregenesis modules)$47K–$93K / TPDBased on 400 TPD design throughput; Class 2 Β±15%
How to Read This CAPEX
The Pregenesis module CAPEX covers feedstock intake and preparation only β€” the physical front-end of the ACM Modular Factory. The manufacturing value creation occurs downstream in the Regenesis Protocol (Total Material Conversion) and Regenesis MAX (OmniCrudeβ„’ refining). Pregenesis module CAPEX should be evaluated as intake infrastructure cost, not as the basis for revenue return calculations. Revenue is generated by what happens to the Manufacturing Feedstock after it enters the Regenesis reactor.
CBT-PRE-CAPEX-001 | Rev 1 | April 2026 | PROPRIETARY β€” CARBOTURA INC.
Class 2 Β±15% | AACE International RP 18R-97 | 2026 USD | RevCon 3 Performance Baseline