Pregenesis Protocol โ Engineering Design Package
Shredder Train โ ASI Procurement Package
Modules 1โ4 | Primary Shredder, Hammermill, Ash Pulverizer, Rotational Mixer & Regenesis Feed Train | Complete OEM fabrication and FAT specification
| Document Number | CBT-EDP-SHRD-001 |
| Parent TDS | CBT-PRE-TDS-003 Rev 1 โ Pregenesis Shredder Train |
| ICD Reference | CBT-PRE-ICD-001 Rev 1 โ Interface Control Document |
| FMEA Reference | CBT-PRE-FMEA-001 Rev 0 โ FMEA Register |
| Governance Prompt | EDP.prompt.md v1.0 โ applied to this document |
| ASI Scope | Factory assembly of all Shredder Train skids to Carbotura OEM specification; FAT per Section 6; Unitized Warranty Passport issued on FAT sign-off |
| Chairman | Allen Witters |
ASI Completeness Requirement
This EDP must be complete enough that the Authorized Strategic Integrator (ASI) can fabricate, assemble, and FAT the Shredder Train module without asking Carbotura Engineering a single question. Any gap in this EDP is a procurement risk and a schedule risk. Open items are tracked with named gates per ICD Rev 1 Open Actions.1. Equipment Identity & ASI Scope
| Equipment Item | Tag Numbers | ASI Scope | Serial No. Format |
|---|---|---|---|
| Tire Pre-Shredder | SHRD-TPS-001/002 | Supply, skid-mount, factory-wire, FAT | CBT-SHRD-TPS-[001/002]-[Year] |
| Primary Shredder + Spring Isolation | SHRD-SHR-001/002 | Supply, skid-mount, inertia base pour, spring isolation install, factory-wire, FAT | CBT-SHRD-SHR-[001/002]-[Year] |
| Magnetic Ferrous Sep. Stage 1 | SHRD-MFS-001/002 | Supply, conveyor-mount, factory-wire, FAT | CBT-SHRD-MFS-[001-004]-[Year] |
| Hammermill + Spring Isolation | SHRD-HMR-001/002 | Supply, skid-mount, inertia base pour, spring isolation install, factory-wire, FAT | CBT-SHRD-HMR-[001/002]-[Year] |
| Magnetic Ferrous Sep. Stage 2 | SHRD-MFS-003/004 | Supply, conveyor-mount, factory-wire, FAT | CBT-SHRD-MFS-[001-004]-[Year] |
| Ash Pulverizer (VRM) | SHRD-APZ-001/002 | Supply, skid-mount, ATEX enclosure integration, factory-wire, FAT | CBT-SHRD-APZ-[001/002]-[Year] |
| Ash Storage Silos | SHRD-ASL-001/002 | Supply, foundation bolt pattern, bin vent filter install, factory-wire, FAT | CBT-SHRD-ASL-[001/002]-[Year] |
| Loss-in-Weight Feeders | SHRD-LWF-001/002/003/004 | Supply, skid-mount, gravimetric calibration at FAT, factory-wire | CBT-SHRD-LWF-[001-004]-[Year] |
| Rotational Mixer | SHRD-MXR-001/002 | Supply, skid-mount, factory-wire, FAT blend uniformity test | CBT-SHRD-MXR-[001/002]-[Year] |
| Regenesis Feed Metering Bin | SHRD-RFB-001/002 | Supply, skid-mount, level instrument install, factory-wire, FAT | CBT-SHRD-RFB-[001/002]-[Year] |
| Enclosed Belt Conveyors (all) | SHRD-CV-001 through -007 | Supply, assembly, APS flange weld, factory-wire | CBT-SHRD-CV-[001-007]-[Year] |
2. Design Standards & Applicable Codes
| Standard | Application |
|---|---|
NFPA 652 (2019) | Combustible Dust โ primary governing standard for ash pulverizer zone (Z-03/Z-04) |
NFPA 68 (2018) | Explosion Protection by Deflagration Venting โ ash pulverizer, silos, hammermill |
NFPA 91 (2015) | Exhaust Systems for Air Conveying of Vapors, Gases, Mists, and Particulate Solids โ all APS conveyor enclosures |
NFPA 70 (NEC) Art. 500โ502 | Electrical โ Class II Div 1 and Div 2 requirements for APZ/ASL zones |
CEMA Belt Conveyor Standards | All enclosed belt and drag-chain conveyors; transfer chute design |
ISO 10816-3 | Mechanical vibration โ spring isolation FAT verification and SCADA alarm setpoints |
ANSI/ISA-84.00.01 (IEC 61511) | Safety Instrumented Systems โ all SIL 1 interlock functions (Nโ low-flow, E-stop chain) |
OSHA 29 CFR 1910 | General industry โ LOTO (1910.147), machine guarding (1910.212), confined space (1910.146) |
ANSI/ISA-5.1-2024 | Instrumentation Symbols and Identification โ all instrument tags |
IBC 2021 Chapter 16 / ASCE 7-22 | Seismic โ spring isolation horizontal restraint design |
ACI 318-19 Appendix D | Concrete anchor design โ spring mount Hilti Kwik Bolt TZ anchors |
AACE International RP 18R-97 | Cost Estimate Classification โ Class 2 estimate basis for this EDP |
3. Equipment Specification Summary
Detailed equipment specifications are in CBT-PRE-TDS-003 Rev 1 Section 6. This EDP section cross-references and adds ASI fabrication-specific requirements not in the TDS.
3.1 Primary Shredder โ ASI Fabrication Requirements
| Requirement | Specification | Verification |
|---|---|---|
| Inertia base concrete pour | Class 4000; poly fiber-reinforced 1.5 lb/ydยณ; #5 rebar 8-in. O.C.; 28-day cure minimum before FAT load test | Concrete test cylinders โ 3ร per pour; 28-day strength report submitted to Carbotura Engineering before FAT |
| Spring mount installation torque | Leveling bolt torque per Kinetics/Mason IOM; all 8 mounts within ยฑ5% of target deflection at operating weight | Deflection measurement report at full weight โ ASI PE sign-off |
| Skid paint / corrosion protection | SSPC-SP6 surface prep; 2-coat epoxy primer + polyurethane topcoat; minimum 6 mil DFT total | Wet film gauge measurements; holiday test per NACE SP0188 |
| ASI-PWR-480-3PH-60A installation | Factory-installed on skid junction box; hi-pot test 1,000V DC per UL 50E before shipment | Hi-pot test certificate submitted with Unitized Warranty Passport |
| Nameplates | Stainless steel, laser-engraved; must include: Serial Number, Carbotura tag number, OEM model, rated kW, voltage, date of FAT completion | Visual inspection at FAT; photograph archived in Unitized Warranty Passport |
4. Motor Schedule
| Tag | Service | kW (P50/Peak) | Voltage | Enclosure | VFD | Service Factor |
|---|---|---|---|---|---|---|
| SHRD-TPS-001M | Tire Pre-Shredder | 90โ132 / 150 | 480V / 3ฮฆ / 60Hz | TEFC | Yes | 1.15 |
| SHRD-SHR-001M | Primary Shredder #1 (hydraulic) | 290 / 380 | 480V / 3ฮฆ / 60Hz | TEFC | Via hydraulic | 1.15 |
| SHRD-SHR-002M | Primary Shredder #2 (hydraulic) | 290 / 380 | 480V / 3ฮฆ / 60Hz | TEFC | Via hydraulic | 1.15 |
| SHRD-HMR-001M | Hammermill #1 | 265 / 330 | 480V / 3ฮฆ / 60Hz | TEFC | Soft-start | 1.25 |
| SHRD-HMR-002M | Hammermill #2 | 265 / 330 | 480V / 3ฮฆ / 60Hz | TEFC | Soft-start | 1.25 |
| SHRD-APZ-001M | VRM Ash Pulverizer #1 | 185 / 235 | 480V / 3ฮฆ / 60Hz | XPFC (Class II Div 1) | Yes | 1.15 |
| SHRD-APZ-002M | VRM Ash Pulverizer #2 | 185 / 235 | 480V / 3ฮฆ / 60Hz | XPFC (Class II Div 1) | Yes | 1.15 |
| SHRD-MXR-001M | Rotational Mixer #1 | 115 / 155 | 480V / 3ฮฆ / 60Hz | TEFC | Yes | 1.15 |
| SHRD-LWF-001/002M | Loss-in-Weight Feeders (2 active) | 7.5 each / 11 | 480V / 3ฮฆ / 60Hz | TEFC | Yes | 1.15 |
| SHRD-CV-xxx-M | Conveyors (7 total) | 5โ30 each | 480V / 3ฮฆ / 60Hz | TEFC | Yes (variable) | 1.15 |
All motors: NEMA Premium Efficiency (IE3 equivalent); frame-agnostic with dimensional envelope specified; VFD-compatible winding insulation per NEMA MG1 Part 31 where VFD is specified. Hammermill motors: high-inertia soft-start; confirm WKยฒ (flywheel effect) with OEM before procurement.
5. Instrument List (Key Items)
| Tag (ISA 5.1) | Service | Type | Output | Zone |
|---|---|---|---|---|
| FIT-SHRD-001 | Feedstock belt scale โ Trough 1 discharge | Belt weigh feeder | 4โ20 mA TPH โ AFR SCADA | General |
| AT-SHRD-APZ-001 | LEL analyser โ APZ Zone Z-03 | Catalytic combustion LEL | 4โ20 mA 0โ100% LEL โ SCADA; 25% alarm, 40% trip | Class II Div 1 |
| AT-SHRD-APZ-002 | Residual Oโ analyser โ APZ Zone Z-03 | Electrochemical Oโ | 4โ20 mA 0โ25% Oโ โ SCADA; >2% vol โ APZ e-stop | Class II Div 1 |
| VT-SHRD-SHR-001 | Vibration โ SHR-001 bearing housing | Wilcoxon 797 triaxial accelerometer | 4โ20 mA 0โ1g RMS; alarm 4mm/s, trip 7.1mm/s | General |
| VT-SHRD-HMR-001 | Vibration โ HMR-001 bearing housing | Wilcoxon 797 triaxial accelerometer | 4โ20 mA 0โ1g RMS; alarm 4mm/s, trip 7.1mm/s | General |
| LT-SHRD-ASL-001 | Ash silo level โ Stream A silo | Continuous radar level transmitter | 4โ20 mA 0โ100% โ SCADA; HIGH 80%, LOW 20%, LOW-LOW 10% | Class II Div 2 |
| LT-SHRD-RFB-001 | Regenesis Feed Bin level | Continuous ultrasonic level | 4โ20 mA; HIGH/LOW discrete alarms via ASI-DAT-MOD-TCP | General |
| PT-SHRD-N2-001 | Nโ supply pressure โ Z-03 inerting header | Pressure transmitter | 4โ20 mA 0โ10 bar; SIL 1 interlock: <5.5 bar โ APZ start permissive BLOCK | Class II Div 1 |
| AT-SHRD-SHR-001 | CO monitor โ Primary Shredder enclosure | Electrochemical CO | 4โ20 mA 0โ500 ppm; 25 ppm alarm, 100 ppm trip โ enclosure CO purge | General |
6. ASI Factory Acceptance Test (FAT) Plan
Mandatory FAT โ Before Any Module Ships
No Shredder Train module may be shipped without a completed FAT signed by the ASI PE and Carbotura Engineering Lead. The Unitized Warranty Passport is issued only after FAT sign-off. All FAT documentation is archived in the Unitized Warranty Passport and in CBT document control.| FAT Hold Point | Description | Acceptance Criteria | Witness |
|---|---|---|---|
| HP-1 | Material certification review โ steel, concrete, gaskets, spring mounts | All materials certify to specified ASTM/ASME standards; concrete 28-day strength โฅ4,000 psi | Carbotura Engineering Lead |
| HP-2 | Dimensional inspection โ skid envelope, nozzle schedule, anchor bolt pattern, nameplate | All dimensions within ยฑ1/8 in. of drawing; nameplate present and legible; anchor pattern per PE-stamped drawing | Carbotura Engineering Lead |
| HP-3 | Spring isolation โ static load test and deflection measurement | All 8 mounts deflect within ยฑ10% of calculated value at operating weight; leveling within ยฑ0.005 in./ft | Carbotura Engineering Lead + ASI PE |
| HP-4 | Electrical โ hi-pot test, continuity, polarity, E-stop functional test | Hi-pot 1,000V DC on all ASI-PWR-480-3PH connections; all E-stop pull cords interrupt drive command within 200 ms; no continuity faults | Carbotura Controls Engineer |
| HP-5 | Modbus TCP/IP โ loop-check all I/O against SCADA tag list | 100% of I/O points confirmed; AFR control loop response โค20 ms; watchdog timeout confirmed | Carbotura Controls Engineer + ASI SCADA Team |
| HP-6 | Dynamic run test โ shredder + spring isolation vibration at rated load | fn <1 Hz (shredder); isolation efficiency โฅ93% at 2 Hz; floor transmitted force โค7% at 2 Hz; noise โค85 dB(A) at 3 ft | Carbotura Engineering Lead + ASI PE (third-party acoustic engineer for dB measurement) |
| HP-7 | APS duct flanges โ smoke pressurization leak test | No visible smoke leak at any ASI-APS-FLG joint at โ3.0 in. WC; VAV valve 0โ100% stroke confirmed; flow element calibration certificate present | Carbotura APS Engineer |
| HP-8 | Loss-in-weight feeder calibration | All 4 feeders within ยฑ0.5% of setpoint across operating range; calibration certificate per OEM procedure | Carbotura Controls Engineer |
| HP-9 | Nโ inerting SIL 1 interlock functional test | Low Nโ pressure (<5.5 bar) confirmed to block APZ start permissive within 2 seconds; Oโ analyser response tested with certified gas standard | Carbotura Safety Lead + ASI PE |
| FAT CLOSE | Unitized Warranty Passport package assembly and sign-off | All HP-1 through HP-9 documentation complete; all deficiencies resolved; ASI PE and Carbotura Engineering Lead signatures on FAT certificate | ASI PE + Carbotura Engineering Lead + Chairman (Allen Witters) if requested |
7. Vendor Selection Matrix
| Equipment | Preferred Vendors | OEM Guarantee | Lead Time | Selection Criteria Weight |
|---|---|---|---|---|
| Primary Shredder | Vecoplan VEZ 3200 / Lindner Polaris 2800 / SSI PRI-MAX PR4400 | Yes โ all three | 26โ32 weeks | Technical compliance 40%, OEM guarantee 20%, lead time 20%, support network 20% |
| Hammermill | Stedman Grand Slam / Metso Lindemann LIS | Yes โ both | 20โ26 weeks | Same as shredder weighting |
| VRM Ash Pulverizer | Pfeiffer MPS 2000 / Loesche LM 15.2 | Yes โ both | 32โ40 weeks (critical path) | Grindability test result is deciding factor; test before final OEM selection |
| Rotational Mixer | Readco Kurimoto / BHS-Sonthofen DKXC | Readco: No / BHS: Yes | 18โ24 weeks | CV <5% FAT guarantee required; BHS preferred if budget permits |
| Magnetic Ferrous Separators (4ร) | Eriez (US supply) / Bunting Magnetics (US) / Goudsmit (European) | Yes โ all three | 8โ14 weeks | Short lead time; US service network preferred; Stage 2 needs high-intensity RE magnet |
| Loss-in-Weight Feeders | Schenck Process MULTICOR K / Coperion K-Tron K2-ML-D5 | Yes โ both | 14โ18 weeks | ยฑ0.5% accuracy guarantee required; both qualify |
8. Warranty Requirements
| Equipment | Required Warranty Period | Coverage Scope | Response Time (Criticality A) |
|---|---|---|---|
| Primary Shredders (2ร) | 24 months from Mechanical Completion | Cutter assembly, hydraulic drive, rotor, bearings, enclosure | 24 hr notification response; 72 hr on-site |
| Hammermills (2ร) | 24 months | Hammers, grates, screens (manufacturing defects โ not wear consumables), drive | 24 hr / 72 hr on-site |
| VRM Ash Pulverizers (2ร) | 24 months | Rollers, grinding table, classifier, drive (excludes wear rate โ separately modeled) | 48 hr / 96 hr on-site |
| Rotational Mixer (1ร) | 18 months | Drum, paddles, drive, end seals | 48 hr / 96 hr on-site |
| Spring Isolation Systems (all) | 36 months from Mechanical Completion | Spring fatigue, weld integrity, leveling mechanism โ extends module warranty by 12 months | Per ASI service agreement |
| All ASI-DAT-MOD-TCP-M12 modules | 24 months | Hardware, gateway, M12 connectors, factory configuration | Remote support 4 hr; on-site 72 hr |
Unitized Warranty Passport โ Required Contents
The Unitized Warranty Passport issued by the ASI upon FAT completion must contain: (1) FAT completion certificate with all HP-1 through HP-9 results; (2) All material certification documents; (3) Concrete inertia base test cylinder reports; (4) Spring isolation deflection measurement report with ASI PE signature; (5) Electrical hi-pot test certificates; (6) Modbus I/O loop-check report; (7) APS duct flange leak test reports; (8) Feeder calibration certificates; (9) SIL 1 interlock test report; (10) Acoustic measurement report; (11) OEM warranty certificates (all equipment); (12) All ASI-issued serial numbers per Section 1.
END OF DOCUMENT โ CBT-EDP-SHRD-001 | Rev 0 | April 2026 | CONFIDENTIAL โ CARBOTURA INC.