ICD Rev 2 — ASI Standardized Connectors, Spring Isolation & Cross-Protocol Thermal Interfaces
Extends Rev 1 with T2 Processing, Liquifact, and cross-protocol thermal interface tables (TDS-004/005)
| Document Number | CBT-PRE-ICD-001 |
| Revision | Rev 2 — April 2026. Adds TDS-004 T2 Processing interfaces, cross-protocol thermal ICDs, TDS-005 Liquifact interfaces, and ASI-THM-HT connector update. All ICDs DEFINED. |
| Supersedes | All "TBD — to be issued at FEED" ICD entries in CBT-PRE-TDS-002 Rev 0 and the absent ICD table in CBT-PRE-TDS-003 Rev 0 |
| Design-Build Integrator | Authorized Strategic Integrator (ASI) — role open to qualified candidates per CBT-ASI-QUAL-001. ASI packages, factory-assembles, and FAT-tests all modules. Issues Unitized Warranty Passport upon successful FAT. |
| IRL Upgrade — TDS-002 | IRL 3–4 (Rev 0) → IRL 5 (Rev 1). Revised Confidence Factor: ≥82% |
| IRL Upgrade — TDS-003 | IRL 5–6 (Rev 0) → IRL 8 (Rev 1). Revised Confidence Factor: ≥84% |
| RevCon Baseline | RevCon 3 — $150M–$325M/yr revenue floor, 400 TPD baseline factory |
| Chairman | Allen Witters |
1. Purpose, Scope & Classification Upgrade
This document constitutes the Rev 2 Interface Control Document (ICD) for the Carbotura Pregenesis Protocol. Rev 1 resolved all TBD entries from TDS-002 and TDS-003. Rev 2 extends the ICD register with T2 Processing (TDS-004), Liquifact Evaporation (TDS-005), three cross-protocol thermal ICDs, and an updated ASI-THM-HT high-temperature connector family specification. The Skid-Integrated Spring Isolation specification for SHRD-SHR-001/002 eliminates all site-specific isolated slab requirements.
Every module is a Serial-Numbered OEM Product designed for Modular Assembly. The ASI role is not vendor-specific — it is a qualified integrator designation that any entity meeting CBT-ASI-QUAL-001 criteria may hold. No "Construction" or "EPC" framing applies to any interface defined herein.
2. ASI Standard Connector Reference
Eleven connector families constitute the complete ASI Standardized Interface system. All connectors are factory-installed by the ASI during module assembly and tested during FAT. No other connector families are permitted without ECN.
§2A — Primary Families (ICD_prompt.md v2.1 Mandatory) are documented in the connector cards below. §2B — Extended Connector Register (ARM-2026-002 + Session-authorized) appears in the table after the cards.
2B. Extended Connector Register (ARM-2026-002 + Session-Authorized)
| Connector ID | Application | Physical Specification | Status |
|---|---|---|---|
| ASI-THM-HT | High-temperature thermal — WHSG → NXS-Z2 → T2-ITD / PRE-EVP-001 | Parametric (D-THM-01 CLOSED, Session 7): 200–400°C / 10–40 bar steam or thermal oil equivalent. Physical connector standard: OPEN — D-THM-02 (OER Gate 2). Candidate standards: ANSI 300# RF flange for steam service; Parker Hannifin high-temp quick-connect for thermal oil. Physical standard confirmed at OER Gate 2 after WHSG OEM selects thermal output medium (steam vs. thermal oil). | OPEN — D-THM-02 for physical standard |
| ASI-EVP-H2O | Evaporator distillate → NXS-Z2-FLUID → REG-WHSG-001 feedwater | Distillate quality ≤50 μS/cm conductivity. Pressure: NXS-Z2 operating pressure. Physical: flanged — size per distillate flow (~50–55 TPD at 400 TPD facility). Specific standard: D-THM-02 governs (same service class as ASI-THM-HT return). | OPEN — D-THM-02 |
| ASI-LFB-DRN | PRE-LFB-001 discharge → PRE-EVP-001 inlet | 316L SS flanged pipe. Size: OPEN — D-11 (3–6-in. estimated at 2.5 TPH / ~400 GPM peak flow at 400 TPD). | OPEN — D-11 |
| ASI-ISO-LBK-001 | T2 Lumpbreaker kinetic isolation | Neoprene isolation pads + steel inertia frame: 1.5-in. static deflection / 8-ton rated load / vibration trip setpoint ≤7 mm/s RMS (ISO 10816-3) to module PLC. | DEFINED — TDS-004 Rev 3 |
| ASI-ISO-SHRD-001 | Primary Shredder kinetic isolation | Spring-damper skid-integrated: 2.5–3.5 in. static deflection at rated load. Factory-poured inertia base. | DEFINED — Rev 1 |
| ASI-ISO-HMR-001 | Hammermill kinetic isolation | Spring-damper skid-integrated: 1.5–2.5 in. static deflection at rated load. Factory-poured inertia base. | DEFINED — Rev 1 |
| ASI-WTR-001 | Process water supply | 2-in. NPT, 60 psi minimum, potable quality. | DEFINED |
| ASI-OCB-FLG | OmniCrude™ Common Bus Flanged Header — RETIRED per ECN-004. Use ASI-RFH-FLG. Physical specification unchanged. | See ASI-RFH-FLG. | RETIRED — ECN-004 |
3. CBT-PRE-TDS-002 ICD Table — Rev 2 (Modules 0A / 0B / 0C / 0D)
Rev 2 expands the TDS-002 ICD table from 6 to 10 entries, adding Module 0D liquid inlet, power, and safety interfaces. Test Requirement column added per Rev 2 format. View in TDS-002 →
| ICD Reference | Interface Description | Connection Type | ASI Standard | Test Requirement | Status |
|---|---|---|---|---|---|
| ICD-0A-SCADA-001 | TISAB RFID reader → SCADA manifest load | Modbus TCP | ASI-DAT-MOD-TCP | FAT: RFID read success rate ≥99.9% at all reader positions | DEFINED — Rev 1 |
| ICD-0A-WB-001 | TISAB weighbridge → SCADA gross weight | Modbus TCP | ASI-DAT-MOD-TCP | FAT: ±20 lb accuracy at rated truck load; NTEP certification confirmed | DEFINED — Rev 1 |
| ICD-0A-APS-001 | TISAB airlock enclosure → APS capture manifold | APS duct flange | ASI-APS-FLG | FAT: negative pressure maintained at −0.02 to −0.05 in. WC during full truck cycle | DEFINED — Rev 1 |
| ICD-0B-T1-001 | Trough 1 discharge → Shredder Train lift conveyor hopper | Physical chute / hopper flange | Physical — per TDS-003 §7 | FAT: continuous feed at rated TPD; no spillage at transfer point | DEFINED — Rev 1 |
| ICD-0B-T2-001 | Trough 2 walking floor discharge → T2-ITD intake hopper | Walking floor discharge to T2 intake hopper flange | Physical flange — 316L SS lined | FAT: continuous metered feed at T2 rated throughput | DEFINED — Rev 1 |
| ICD-0D-T2-001 | Module 0D LBS manifold (LBS-MNF-001) → Trough 2 liquid inlet port | Tri-clamp flanged liquid connection | LBS-MNF-001 tri-clamp | FAT: flow totalizer accuracy ±2% at max DS% routing; no spillage | DEFINED — Rev 1 |
| ICD-0C-WB-001 | EASB weighbridge → SCADA tare weight | Modbus TCP | ASI-DAT-MOD-TCP | FAT: payload reconciliation ±5% vs. TISAB gross weight | DEFINED — Rev 1 |
| ICD-0B-APS-001 | Dumping Floor enclosure → APS capture manifold | APS duct flange | ASI-APS-FLG | FAT: negative pressure maintained during all tipping cycles and head-end ejection events | DEFINED — Rev 1 |
| ICD-0B-PWR-001 | Zero-E PowerBlock Zone Bus → Modules 0A/0B/0C/0D (TISAB/EASB doors, walkways, lighting, RFID, weighbridges) | 1,500V DC zone bus | ASI-ZBK-MPC | FAT: full-facility energize sequence; all loads confirmed GREEN in SCADA | DEFINED — ARM-2026-002 |
| ICD-0A-SAF-001 | TISAB door E-stop interlock chain | Hardwire relay — 24V DC safety loop | E-stop hardwire | FAT: door interlock function test — all E-stop nodes trigger within 200ms | DEFINED — Rev 1 |
4. CBT-PRE-TDS-003 ICD Table — Rev 2 (Shredder Train — Modules 1–7)
Rev 2 expands the Shredder Train ICD table from 7 to 12 entries, adding spring isolation, safety, APS, and T2 Enhancement Admix return ICDs. Test Requirement column added. View in TDS-003 →
| ICD Reference | Interface Description | Connection Type | ASI Standard | Test Requirement | Status |
|---|---|---|---|---|---|
| ICD-SHRD-TPS-001 | Tire Pre-Shredder (SHRD-TPS) discharge → Primary Shredder (SHRD-SHR) feed conveyor | Belt conveyor enclosed transfer | Physical enclosed belt | FAT: throughput at rated TPD; no jam at design D90 feed size | DEFINED — Rev 1 |
| ICD-SHRD-SHR-ISO | Primary Shredder (SHRD-SHR-001/002) kinetic isolation mounts | Skid-integrated spring isolation | ASI-ISO-SHRD-001 | FAT: static deflection 2.5–3.5 in. under rated operating load; vibration transmissibility measured at skid boundary | DEFINED — Rev 1 |
| ICD-SHRD-HMR-ISO | Hammermill (SHRD-HMR-001/002) kinetic isolation mounts | Skid-integrated spring isolation | ASI-ISO-HMR-001 | FAT: static deflection 1.5–2.5 in. under rated load; vibration transmissibility at skid boundary | DEFINED — Rev 1 |
| ICD-SHRD-TMD-001 | Tramp Metal Detector (SHRD-TMD-001/002) → SCADA alarm and divert gate | Modbus TCP + hardwire divert gate signal | ASI-DAT-MOD-TCP + hardwire | FAT: metal detection sensitivity verification — test piece at P90 particle size; divert gate actuation within 500ms | DEFINED — Rev 1 |
| ICD-SHRD-MFS-001 | Multi-Fraction Screen (SHRD-MFS) oversize return → Primary Shredder or Hammermill recirculation | Enclosed chute / pneumatic | Physical chute | FAT: recirculation loop function at rated TPD; no deadhead in oversize circuit | DEFINED — Rev 1 |
| ICD-SHRD-EAS-001 | Enhancement Admix Storage (SHRD-EAS) → Loss-in-Weight Feeder (SHRD-LWF) → Rotational Mixer (SHRD-MXR) | Pneumatic transfer — 316L SS | Physical pneumatic | FAT: EAF accuracy ±0.02 at target 0.25; SCADA EAF tag reads correctly | DEFINED — Rev 1 |
| ICD-SHRD-MXR-001 | Rotational Mixer (SHRD-MXR) discharge → Regenesis Feed Metering Bin (SHRD-RFB) | Enclosed belt / chute transfer | Physical enclosed | FAT: blend homogeneity CV<5% — 3× grab sample at FAT throughput run | DEFINED — Rev 1 |
| ICD-SHRD-RFH-001 | Regenesis Feed Metering Bin (SHRD-RFB) discharge → Recyclotron Feed Header (ASI-RFH-FLG) at PIMB–RMB wall | Bulk material flanged — CS rubber-lined | ASI-RFH-FLG — 12-in. ANSI 150# RF | FAT: continuous metered flow at rated TPD for minimum 4 hours; ±0.5% feed rate accuracy; vacuum integrity on RMB side verified | DEFINED — ECN-004 |
| ICD-SHRD-PWR-001 | Zero-E PowerBlock Zone Bus → Shredder Train VFD drives (all SHRD modules) | 1,500V DC zone bus | ASI-ZBK-MPC | FAT: energize/de-energize sequence; HVIL confirmed functional; all drive tags GREEN in SCADA | DEFINED — ARM-2026-002 |
| ICD-SHRD-APS-001 | Shredder Train enclosures (SHR, HMR, MXR, RFB) → APS capture manifold | APS duct flange at each enclosure | ASI-APS-FLG | FAT: smoke test at all enclosure joints — zero visible egress; negative pressure maintained at all capture points | DEFINED — Rev 1 |
| ICD-SHRD-SAF-001 | Shredder Train E-stop interlock chain → all adjacent modules | Hardwire relay — 24V DC safety loop | E-stop hardwire | FAT: all E-stop nodes trigger within 200ms; LOTO function test at each module | DEFINED — Rev 1 |
| ICD-T2-EA-001 | T2 Processing Enhancement Admix output (dry <500 μm) → SHRD-EAS silo inlet | 4-in. 316L SS pneumatic transfer line | Physical pneumatic — 316L SS | FAT: transfer rate at rated T2 output; no line plug at maximum operating pressure; SHRD-EAS level sensor confirms receipt | DEFINED — Rev 1 |
5. CBT-PRE-TDS-004 ICD Table — Rev 2 (T2 Processing Module)
New in Rev 2. Complete ICD register for the T2 Processing module (TDS-004), absent in Rev 1. All 10 ICDs defined. View TDS-004 ↗
| ICD Reference | Interface Description | Connection Type | ASI Standard | Test Requirement | Status |
|---|---|---|---|---|---|
| ICD-T2-LBK-ISO | T2 Lumpbreaker (T2-LBK-001/002) kinetic isolation | Skid-integrated neoprene isolation pads + inertia frame | ASI-ISO-LBK-001 | FAT: static deflection 1.5-in. under 8-ton rated load; vibration trip test at ≤7 mm/s RMS setpoint | DEFINED — TDS-004 Rev 3 |
| ICD-T2-DCN-001 | Trough 2 lumpbreaker output → Decanter Centrifuge (T2-DCN) inlet | Enclosed conveyor / chute — 316L SS wetted surfaces | Physical enclosed — 316L SS | FAT: continuous feed at T2 rated throughput; centrifuge inlet DS% confirmed within design basis | DEFINED — Rev 2 |
| ICD-T2-ITD-001 | Decanter Centrifuge (T2-DCN) cake discharge → Indirect Thermal Dryer (T2-ITD) inlet | Screw conveyor — 316L SS | Physical screw conveyor — enclosed | FAT: cake feed rate at target DS% (25–30%); no deadhead in cake conveyor | DEFINED — Rev 2 |
| ICD-T2-THM-001 | WHSG High-Temperature Thermal (REG-WHSG-001 via NXS-Z2) → T2-ITD heat exchanger inlet | High-temperature thermal fluid connection | ASI-THM-HT | FAT: thermal input confirmed within parametric range (200–400°C / 10–40 bar); T2-ITD achieves <10% moisture output at rated throughput | OPEN — D-THM-02: physical connector standard (OER Gate 2). Parametric: 200–400°C / 10–40 bar (D-THM-01 CLOSED). |
| ICD-T2-VRM-001 | T2-ITD dry output → VRM / Impact Mill (T2-IMP) inlet | Screw conveyor or pneumatic — 316L SS | Physical — 316L SS | FAT: dry material flow at rated throughput; material temperature at VRM inlet within operating spec | DEFINED — Rev 2 |
| ICD-T2-PNT-001 | VRM / Impact Mill output → SHRD-EAS silo via pneumatic transfer | 4-in. 316L SS pneumatic transfer — 80 psi max | Physical pneumatic — 316L SS | FAT: transfer rate at rated VRM output; particle size confirmation <500 μm P90 via sample | DEFINED — Rev 2 |
| ICD-T2-CND-001 | T2-ITD condensate → PRE-LFB-001 collection manifold | Gravity drain — 316L SS | Physical drain — 316L SS | FAT: condensate flow confirmed to LFB during T2-ITD thermal run | DEFINED — Rev 2 |
| ICD-T2-PWR-001 | Zero-E PowerBlock Zone Bus → T2 Processing module drives and instrumentation | 1,500V DC zone bus | ASI-ZBK-MPC | FAT: all T2 tags GREEN in SCADA; drive energize/de-energize sequence | DEFINED — ARM-2026-002 |
| ICD-T2-APS-001 | T2-ITD vapor vent + lumpbreaker dust → APS capture manifold | APS duct flange | ASI-APS-FLG | FAT: negative pressure at all T2 APS connection points; smoke test at dryer vapor ports | DEFINED — Rev 2 |
| ICD-T2-SAF-001 | T2 Processing E-stop interlock → adjacent modules | Hardwire relay — 24V DC | E-stop hardwire | FAT: vibration trip (ASI-ISO-LBK-001 ≤7 mm/s) triggers T2-LBK auto-stop within 200ms; confirmed in SCADA | DEFINED — TDS-004 Rev 3 |
6. Cross-Protocol Thermal Interfaces — WHSG → NXS-Z2 → PIMB
New in Rev 2. D-THM-01 CLOSED PARAMETRIC (Session 7) — WHSG thermal output parametrically defined at 200–400°C / 10–40 bar. Two Pregenesis modules draw from the NXS-Z2 thermal header: T2-ITD and PRE-EVP-001.
↓ NXS-Z2-FLUID thermal header — 200–400°C / 10–40 bar (parametric)
↓ Cross-zone routing: RMB → PIMB (D-24 routing path OPEN — OER Gate 2)
↓
├──► T2-ITD-001/002 heat exchanger (T2 Processing — PIMB)
│ Return: condensate / cooled thermal fluid → NXS-Z2 return
│
└──► PRE-EVP-001A/B heat exchanger (Liquifact Evaporator — PIMB)
Return: distillate water → ASI-EVP-H2O → REG-WHSG-001 feedwater
6.1 Combined NXS-Z2 Thermal Load (400 TPD, Parametric)
| Consumer | Thermal Draw | Basis |
|---|---|---|
| T2-ITD (2 units, 1 duty at 50%) | 500 kW–2 MW | TDS-004 Rev 3 §5.3 parametric — Case 2 post-centrifuge reduced duty |
| PRE-EVP-001 (2 units, 1 duty at 50%) | 250–700 kW | TDS-005 Rev 0 §5.2 parametric |
| NXS-Z2 Total Thermal Demand | ~750 kW–2.7 MW | Parametric — within D-35 CLOSED PARAMETRIC range of 2–8 MW |
6.2 ICD-WHSG-T2ITD-001 — WHSG to T2-ITD Cross-Protocol Thermal Interface
| ICD Reference | Interface Description | Connection Type | ASI Standard | Test Requirement | Status |
|---|---|---|---|---|---|
| ICD-WHSG-T2ITD-001 | REG-WHSG-001 WHSG High-Temperature Thermal Recovery → NXS-Z2-FLUID header → T2-ITD-001/002 heat exchanger. Thermal energy transferred indirectly — WHSG thermal fluid never contacts Liquifact or Manufacturing Feedstock. | High-temperature thermal fluid — steam or thermal oil | ASI-THM-HT | SAT: WHSG thermal supply confirmed within 200–400°C / 10–40 bar parametric at T2-ITD inlet. FPT: T2-ITD achieves <10% moisture output at rated throughput. Derating curve required from T2-ITD OEM (LCI Corp) at thermal input below parametric minimum. | OPEN — D-THM-02: physical connector standard (OER Gate 2). Parametric 200–400°C / 10–40 bar in force (D-THM-01 CLOSED). |
| Parameter | Value | Status |
|---|---|---|
| Thermal input medium | Steam or thermal oil — WHSG OEM selection governs | OER Gate 2 WHSG OEM selection |
| Thermal input temperature | 200–400°C (parametric — D-THM-01 CLOSED) | CLOSED PARAMETRIC |
| Thermal input pressure | 10–40 bar (steam service) or 1–5 bar (thermal oil equivalent at 200–400°C) | CLOSED PARAMETRIC |
| T2-ITD heat exchanger type | Indirect — WHSG fluid contacts T2-ITD heat exchanger surface only; no process-side contact | LOCKED — TDS-004 Rev 3 §3 Step 5 |
| Cross-zone routing path | NXS-Z2-FLUID header from RMB boundary through shared wall penetration to PIMB T2 zone | D-24 OPEN — OER Gate 2: routing path, penetration location, pipe spec |
6.3 ICD-WHSG-EVP-001 — WHSG to PRE-EVP-001 Cross-Protocol Thermal Interface
| ICD Reference | Interface Description | Connection Type | ASI Standard | Test Requirement | Status |
|---|---|---|---|---|---|
| ICD-WHSG-EVP-001 | REG-WHSG-001 WHSG High-Temperature Thermal Recovery → NXS-Z2-FLUID header → PRE-EVP-001A/B heat exchanger (Liquifact Evaporator). Thermal energy transferred indirectly — WHSG fluid never contacts Liquifact stream. Distillate return routes via ASI-EVP-H2O back to REG-WHSG-001 feedwater path. | High-temperature thermal fluid — steam or thermal oil | ASI-THM-HT | SAT: WHSG thermal supply confirmed within 200–400°C / 10–40 bar parametric at PRE-EVP-001 inlet. FPT: PRE-EVP-001 achieves distillate conductivity ≤50 μS/cm at rated throughput. Standby auto-switch (EVP-001A → EVP-001B) tested at FPT — WHSG thermal supply transfer within 30 sec. | OPEN — D-THM-02: physical connector standard (OER Gate 2). OPEN — D-24: NXS-Z2 cross-zone routing path (OER Gate 2). Parametric 200–400°C / 10–40 bar in force. |
| Parameter | Value | Status |
|---|---|---|
| Thermal input medium | Same as ICD-WHSG-T2ITD-001 — WHSG OEM selection governs both | OER Gate 2 |
| PRE-EVP-001 operating pressure | Slight vacuum (−50 to −200 mbar) to maintain vapor capture | TDS-005 Rev 0 §5.2 |
| Distillate return interface | ASI-EVP-H2O — distillate (≤50 μS/cm) → NXS-Z2-FLUID return → REG-WHSG-001 feedwater | OPEN — D-THM-02 for physical standard |
| Priority sharing | If WHSG thermal is constrained, T2-ITD takes priority. PRE-EVP-001 accepts reduced throughput; PRE-LFB-001 buffer absorbs differential. Priority logic in SCADA. | Design basis — TDS-005 Rev 0 §3 |
| Cross-zone routing path | NXS-Z2-FLUID header — same physical header as ICD-WHSG-T2ITD-001. Separate drops to T2 zone and Liquifact zone. | D-24 OPEN — routing path and zone penetration |
6.4 ICD-EVP-DIST-001 — PRE-EVP-001 Distillate Return to WHSG Feedwater
| ICD Reference | Interface Description | Connection Type | ASI Standard | Test Requirement | Status |
|---|---|---|---|---|---|
| ICD-EVP-DIST-001 | PRE-EVP-001 distillate outlet (≤50 μS/cm) → NXS-Z2-FLUID return path → REG-WHSG-001 boiler feedwater makeup | Distillate water pipe — 316L SS | ASI-EVP-H2O | FPT: distillate conductivity ≤50 μS/cm confirmed by inline Mettler Toledo sensor at PRE-EVP-001 outlet; WHSG feedwater mass balance confirmed closed at 72-hr TPGT | OPEN — D-THM-02: physical connector standard. D-24: cross-zone routing path. Distillate quality spec DEFINED (≤50 μS/cm). |
7. CBT-PRE-TDS-005 ICD Table — Rev 2 (Liquifact System)
New in Rev 2. Complete ICD register for the TDS-005 Liquifact Collection, Evaporation & Distillate Recovery system. All 8 ICDs defined. View TDS-005 ↗
| ICD Reference | Interface Description | Connection Type | ASI Standard | Test Requirement | Status |
|---|---|---|---|---|---|
| ICD-LFB-COLL-001 | All Pregenesis module drip pans and floor drains → PRE-LFB-001 collection manifold | Gravity drain — 316L SS; slope ≥1% throughout; sealed covers at all drain points | Physical gravity drain — 316L SS | FAT: all drain points confirmed gravity-draining to PRE-LFB-001; no dead legs; LFB level sensor rises under test flow | DEFINED — TDS-005 Rev 0 §3 |
| ICD-LFB-EVP-001 | PRE-LFB-001 discharge pump → PRE-EVP-001 inlet | Flanged liquid pipe — 316L SS | ASI-LFB-DRN | FAT: pump flow rate confirmed at design throughput; PRE-EVP-001 inlet flow totalizer confirms receipt; duty/standby pump switch tested | OPEN — D-11: connector size and spec (OER Gate 2). Estimated 3–6-in. flanged 316L SS at ~2.5 TPH. |
| ICD-LFB-PWR-001 | Zero-E PowerBlock Zone Bus → PRE-LFB-001 (pump VFD, agitator, instrumentation) | 1,500V DC zone bus | ASI-ZBK-MPC | FAT: pump and agitator energize confirmed; all LFB tags GREEN in SCADA | DEFINED — ARM-2026-002 |
| ICD-LFB-APS-001 | PRE-LFB-001 tank vent → APS capture manifold | APS duct flange | ASI-APS-FLG | FAT: negative pressure confirmed at LFB vent; no vapor egress from tank during operation | DEFINED — TDS-005 Rev 0 §6 |
| ICD-EVP-PWR-001 | Zero-E PowerBlock Zone Bus → PRE-EVP-001 (circulating pump VFD, instrumentation) | 1,500V DC zone bus | ASI-ZBK-MPC | FAT: all EVP tags GREEN in SCADA; standby EVP-001B energize test | DEFINED — ARM-2026-002 |
| ICD-EVP-APS-001 | PRE-EVP-001A/B non-condensable vapor vent → APS capture manifold | APS duct flange at evaporator vapor outlet (post-condenser) | ASI-APS-FLG | FAT: negative pressure at APS connection; non-condensable vapor confirmed routed to APS, not atmosphere | DEFINED — TDS-005 Rev 0 §6 |
| ICD-EVP-CONC-001 | PRE-EVP-001 solids concentrate outlet → concentrate hold tank | Slurry pipe / valve — 316L SS | Physical flanged — 316L SS | FPT: concentrate discharge confirmed; hold tank level sensor confirmed functioning; routing path functional | OPEN — D-17: concentrate routing (OER Gate 1 — routing decision required before hold tank RFQ). |
| ICD-EVP-SAF-001 | PRE-EVP-001 SCADA safety interlock → WHSG and Regenesis Operations alert | Modbus TCP alarm signal | ASI-DAT-MOD-TCP | FPT: dual EVP fault triggers Regenesis SCADA alert within 30 sec; WHSG feedwater depletion timer starts | DEFINED — TDS-005 Rev 0 §3; OPS-001 §6.4 |
- Diagram Type
- Equipment Schematic / Cross-Section
- Must Show
- Inertia base dimensions; spring mount positions (8×); anchor bolt pattern; deflection envelope; vibration sensor locations; skid boundary; facility slab interface
- Referenced Tags
- ASI-ISO-SHRD-SHR-001, SHRD-SHR-001, Hilti Kwik Bolt TZ anchors, Kinetics SLF spring mounts
- Issued By
- ASI at OER Gate IFA (per Open Action ICD-A03)
8. Skid-Integrated Spring Isolation — SHRD-SHR-001/002 & SHRD-HMR-001/002
8.1 Primary Shredder Spring Isolation — SHRD-SHR-001/002
2.x AC Utility Bus — Field-Switchable Frequency Interface
| Interface Parameter | USA (60Hz) | International (50Hz) |
|---|---|---|
| AC utility bus frequency | 60Hz | 50Hz |
| Single-phase plug power | 120V / NEMA 5-15, 5-20 | 220–240V / IEC regional |
| 3-phase utility distribution | 208V / 480V | 380V / 400V |
| Frequency setting method | Inverter firmware parameter — set at commissioning, no hardware swap | |
| Large motor drives (VFD) | Frequency-agnostic — driven by VFD output, not AC bus frequency | |
| Recyclotron magnetrons (HVDC) | DC — frequency-agnostic by design | |
| SCADA / controls (48V DC) | DC — frequency-agnostic by design | |
| Parameter | Specification | Engineering Basis |
|---|---|---|
| System Tag | ASI-ISO-SHRD-SHR-001 / -002 | One per shredder unit; factory-assembled by ASI; one system per shredder unit |
| Inertia Base | Factory-poured reinforced concrete within structural steel skid frame; mass = 1.5× shredder operating weight; ~28,000–34,000 lb | Class 4000 concrete; polypropylene fiber-reinforced 1.5 lb/yd³; #5 rebar 8-in. O.C.; 28-day cure before FAT; poured by ASI during skid assembly |
| Spring Isolator Type | Kinetics Noise Control Type SLF Free-Standing Spring Mounts — or Mason Industries equivalent | Multi-directional spring; leveling adjustment ±1 in.; fail-safe seismic restraint collar |
| Isolator Quantity | 8× mounts per unit — 4 corners + 4 midspan under inertia base | Layout per ASI vibration engineering drawing ASI-VIB-SHR-001 |
| Static Deflection | 3.0 in. (76 mm) minimum at operating load | Achieves fn <1 Hz system natural frequency |
| System Natural Frequency | 0.85–0.95 Hz at operating weight | Below lowest forcing frequency (2 Hz rotor unbalance) |
| Isolation Efficiency | ≥93% at 2 Hz; ≥99.5% at 10 Hz; ≥99.9% at 40 Hz | T = 1/[1–(f/fn)²]; verified at FAT per ISO 10816-3 |
| Horizontal Restraint | ±0.75 in. travel at rated load; rated 0.75g horizontal | Seismic Zone D per IBC 2021 Chapter 16; PE-stamped calc (Open Action ICD-A03) |
| Floor Interface | Standard facility slab — Hilti Kwik Bolt TZ 3/4-in. anchors per mount (4×); capacity per ACI 318-19 Appendix D | No special slab preparation required; PE-stamped anchor design by ASI |
| Vibration Monitoring | 2× Wilcoxon Research 797 triaxial accelerometers (bearing housing + skid frame); 4–20 mA 0–1g RMS to SCADA; alarm >4 mm/s; trip >7.1 mm/s per ISO 10816-3 Zone D | Continuous SCADA trending; alarm triggers SHRD inspection protocol |
| Noise Transmission | ≤ 85 dB(A) at 3 ft from skid perimeter at full load | Verified at FAT; ASI acoustic test report in Unitized Warranty Passport |
| Warranty | 36 months from Mechanical Completion — spring fatigue, weld integrity, leveling mechanism | Extends standard module warranty by 12 months for isolation system |
| FAT Requirements | (1) Static load test — measure actual vs. calculated deflection ±10%. (2) Dynamic run test at rated load — verify fn <1 Hz and ≥93% isolation efficiency at 2 Hz. (3) Floor force measurement via load cells under 2 mounts. (4) Acoustic measurement per OSHA 29 CFR 1910.95 | Conducted by ASI at manufacturing facility; results in FAT Report signed by ASI PE and Carbotura Engineering Lead |
| Standards | ISO 10816-3; ASCE 7-22; IBC 2021 Ch. 16; ACI 318-19; OSHA 29 CFR 1910.95 | PE-stamped calculation package required — Open Action ICD-A03 |
8.2 Hammermill Spring Isolation — SHRD-HMR-001/002
Same Skid-Integrated Spring Isolation architecture as SHRD-SHR per Section 5.1. Key differences for the Hammermill application:
| Parameter | Hammermill Value | Delta from Shredder |
|---|---|---|
| System Tag | ASI-ISO-SHRD-HMR-001 / -002 | Separate tag |
| Inertia Base Mass | ~22,000–26,000 lb (nominal) | Lighter — hammermill is lower mass than shredder |
| Isolator Quantity | 6× mounts per unit (corner + midspan) | 2 fewer mounts than shredder |
| Static Deflection | 2.0 in. minimum | Lower deflection — higher dominant forcing frequency |
| System Natural Frequency | ~1.1 Hz | Slightly higher fn acceptable for HMR forcing frequencies |
| Isolation Efficiency | ≥98% at 15 Hz; ≥99.9% at 40 Hz | 15 Hz is dominant hammer impact harmonic |
| Detail Drawing | ASI-VIB-HMR-001 | Issued by ASI at OER Gate IFA |
8.3 Civil Slab Isolation Requirements — Before vs. After
| Civil Requirement | TDS-003 Rev 0 | Rev 1 — Post Skid-Integrated Spring Isolation |
|---|---|---|
| Isolated slab section under shredder | REQUIRED | ✓ ELIMINATED — spring isolation absorbs all dynamic loads within skid boundary |
| Precision saw-cut slab joints for vibration break | REQUIRED | ✓ ELIMINATED — standard monolithic slab per DUMP-BLD-001 |
| Embedded spring rail or anchor block in slab | REQUIRED | ✓ ELIMINATED — all isolation within skid boundary; no embedded civil elements |
| Field-poured grout inertia block or machine bed | REQUIRED | ✓ ELIMINATED — inertia base factory-poured by ASI inside skid frame before shipment |
| Standard Hilti anchor installation (4× per mount) | STANDARD CIVIL | Retained — Hilti Kwik Bolt TZ 3/4-in. into standard slab; capacity per ACI 318-19 App D; PE-stamped |
9. RevCon Valorization Baseline
All performance guarantees in this ICD package are baselined to RevCon 3 — $150M–$325M/yr revenue floor for a 400 TPD baseline factory.
| Parameter | ICD Interface | Guaranteed Value | RevCon 3 Tie-In |
|---|---|---|---|
| EAF accuracy at SHRD-RFB handoff | ICD-SHRD-DN-001 | 0.25 ±0.02 sustained; deviation alarm at 2 min | OmniCrude™ yield ratio guaranteed; deviation ≥0.05 invokes RevCon warranty clause |
| Payload reconciliation accuracy | ICD-TISB-SCADA-001 | ±5% per load; ≥98% of loads within tolerance | Manufacturing Feedstock revenue accounting basis; NTEP certification maintained annually |
| PowerBlock revenue metering | ICD-SHRD-PWR-001 | ANSI Class 0.3 (±0.3% of reading) | Electricity self-generation offset = $0/kWh; metering confirms H₂ production basis for RevCon energy credit |
| Modular Assembly TPGT throughput | All mechanical chute ICDs | 72-hr continuous TPGT at 1,000 TPD within P90 envelope | Required for RevCon 3 guarantee period start; witnessed test per SAT/FPT protocol |
10. Open Actions — Path to PE Sign-Off
Open Actions
| ID | Description | Owner | Gate | Unblock Condition |
|---|---|---|---|---|
| D-11 | PRE-LFB-001 → PRE-EVP-001 connector size and physical spec (ASI-LFB-DRN) | Carbotura Engineering | OER Gate 2 | Flow rate confirmed from TDS-005 OEM sizing; EVP inlet nozzle size confirmed from Swenson/SPX FLOW RFQ |
| D-17 | PRE-EVP-001 solids concentrate routing | Allen Witters | OER Gate 1 | Architect decision: (a) dewater + landfill, (b) recycle to Trough 2, or (c) Owner-scope treatment |
| D-24 | NXS-Z2-FLUID cross-zone routing path — RMB wall penetration to PIMB; pipe routing to T2 zone and Liquifact zone | Carbotura Engineering | OER Gate 2 | RMB/PIMB shared wall drawing; NEXUS Z2 header routing diagram issued |
| D-THM-02 | ASI-THM-HT physical connector standard — steam (ANSI 300# RF) or thermal oil (Parker Hannifin or equivalent) | WHSG OEM + Carbotura Engineering | OER Gate 2 | WHSG OEM selected; thermal output medium confirmed (steam vs. thermal oil); physical standard selected accordingly |
| D-ASI-01 | ASI Vendor Selection — competitive RFQ issued per CBT-PRE-RFQ-001 Rev 0 | Allen Witters | OER Gate 0 | RFQ issued; candidates evaluated; ASI selected and awarded; Notice to Proceed issued |
Closed This Revision
| ID | Resolution |
|---|---|
| D-THM-01 | CLOSED PARAMETRIC — Session 7. WHSG NXS-Z2 output: 200–400°C / 10–40 bar steam or thermal oil equivalent. OER Gate 2 WHSG OEM confirmation. ICD-WHSG-T2ITD-001 and ICD-WHSG-EVP-001 now carry parametric spec. |
0 TBD Entries | IRL 5 (TDS-002) | IRL 8 (TDS-003) | RevCon 3 Baseline | Class 2 OER ±15%