Carbotura
Engineering Portal
Controlled
Pregenesis Protocol โ€” Operational Procedure

Dumping Floor, Trough Feed System
& Exit Airlock Scale Building

Modules 0A (TISAB), 0B (Dumping Floor & Troughs), 0C (EASB) โ€” Complete feedstock intake operations

Doc No.CBT-PRE-OPS-002
RevisionRev 0
StatusIssued for Review
ClassificationControlled
OwnerCarbotura Inc. โ€” Operations
Document Control
Document NumberCBT-PRE-OPS-002
RevisionRev 0 โ€” April 2026
StatusIssued for Review
Parent ProtocolCBT-PRE-OPS-001 (Master Operational Protocol)
Related DocumentsCBT-PRE-TDS-002 (technical basis) ยท CBT-PRE-OPS-003 (downstream Shredder Train) ยท CBT-PRE-OPS-004 (Trough 2 Processing)
ChairmanAllen Witters
Manufacturing Classification Notice
All material received and handled within the boundary of this protocol is classified as Manufacturing Feedstock โ€” an input material for Carbotura Advanced Circular Manufacturing. No waste treatment, storage, or disposal activities are defined or implied.

1. Purpose & Scope

This protocol governs all operational procedures for the Pregenesis feedstock intake, receiving, and trough feed system โ€” from truck arrival at TISAB through Manufacturing Feedstock delivery to the Shredder Train (CBT-PRE-OPS-003) and Trough 2 Processing (CBT-PRE-OPS-004). It covers Modules 0A (TISAB), 0B (Dumping Floor and Troughs), and 0C (EASB).

BoundaryDescription
UpstreamTISAB entry gate (truck arrival from public road)
Downstream (Trough 1)Trough 1 lift conveyor discharge to Shredder Train โ€” governed by CBT-PRE-OPS-003
Downstream (Trough 2)Trough 2 walking floor discharge to T2 Processing โ€” governed by CBT-PRE-OPS-004

2. Definitions

TermDefinition
TISABTruck Intake and Scale Airlock Building โ€” Module 0A. Entry pressure boundary and weighing station.
EASBExit Airlock Scale Building โ€” Module 0C. Exit pressure boundary and tare weight confirmation station.
Airlock SequenceControlled door interlock cycle that maintains negative pressure boundary during truck transit.
Airlock HoldDwell period within the airlock where pressure equalization occurs, weight is captured, and load acceptance is confirmed.
DrawbridgeHydraulically actuated bridge section over each trough that raises 45โ€“70ยฐ to allow truck tipping.
Walking FloorReciprocating slat conveyor at trough bottom. Moves Manufacturing Feedstock toward discharge at SCADA-controlled rate.
Tare ReconciliationSCADA comparison of TISAB gross weight to EASB tare weight to confirm net payload delivered.
Quarantine Bay QA-01Reinforced concrete quarantine pit with water deluge for isolation of energetic or thermal hazard materials.
Manufacturing FeedstockAll input material received at the Pregenesis Dumping Floor. Processed as manufacturing input under Carbotura ACM operations.

3. Pre-Operation Checklist

Mandatory First Step
Do not authorize truck intake or start any equipment until APS is confirmed running and negative pressure is confirmed in the Dumping Floor zone (โ€“0.05 to โ€“0.10 in. WC). This is non-negotiable.
Pre-Operation Checklist โ€” All items must be confirmed before authorizing intake
APS running and negative pressure confirmed (โ€“0.05 to โ€“0.10 in. WC in Dumping Floor)
MANDATORY FIRST โ€” do not proceed if failed
TISAB/EASB door controls enabled โ€” both Lane A and Lane B
All 4 bridge hydraulic power units pressure confirmed on SCADA
All drawbridges DOWN and latched โ€” confirm via position sensors (Trough 1A, 1B, 2A, 2B)
Walking floor systems on STANDBY โ€” Trough 1 and Trough 2
Lift conveyors on STANDBY โ€” Trough 1 lift conveyor
Leachate sump pump on AUTO โ€” Trough 2 sump pump
Magnetic head pulley operational on lift conveyor โ€” confirm running prior to conveyor start
Thermal detection camera active (Li-battery detection at TISAB approach)
MANDATORY โ€” do not accept loads without active thermal screening
Bay assignment system and LED signage active โ€” test bay assignment display
SCADA truck routing system active โ€” manifest loading confirmed
Ferrous collection bins FCB-001/002 below HIGH alarm โ€” empty if near HIGH

4. Truck Routing Protocol

4.1 Manifest-Based Lane and Bay Assignment

Material TypeTrough AssignmentBay Assignment Logic
Manufacturing Feedstock (MSW)Trough 1SCADA assigns specific bay for even distribution
Sludge or AshTrough 2SCADA assigns bay based on trough level and NIR zone
MixedPer programmed split ratioSCADA assigns partial loads per trough demand
PROHIBITEDDivert โ€” do not enterTruck diverted at entry gate before any door opens

4.2 Normal Intake Sequence

Truck arrives at facility gate โ€” transponder or RFID reads manifest. Bay assignment pre-loaded.
Traffic control assigns Lane A or Lane B. Entry door status check: entry door OPEN, exit door CLOSED and SEALED.
Truck advances onto scale pit โ€” entry door closes and seals behind truck.
AIRLOCK HOLD: 15-second pressure equalization cycle. TISAB fans balance to โ€“0.02 to โ€“0.05 in. WC relative to outside. Do not open exit door until equalization complete.
Gross weight measured ยฑ20 lb, tare subtracted, net payload calculated and logged to SCADA.
Load acceptance check: manifest match confirmed, weight within range, no prohibited materials flag.
Exit door opens โ€” truck advances onto Dumping Floor. Exit door closes behind truck โ€” lane reset initiated.
SCADA displays bay assignment on LED signage. Truck drives to assigned bay and tips load.
Empty truck drives toward EASB for exit via Section 9 protocol.

5. Airlock Door Interlock State Machine

State Machine Scope
The following 8-state machine (STATE 0 through STATE 7) governs all TISAB and EASB door operations. No door movement is permitted outside this state machine logic. This applies to both Lane A and Lane B independently.
StateDescriptionEntry ConditionExit ConditionAction Permitted
STATE 0Both doors closed โ€” standbyDefault on power-up or lane resetRaise request + all interlocks clearNone
STATE 1Entry door openingAll interlocks confirmed clearEntry door fully open confirmed by sensorTruck enters
STATE 2Truck entering โ€” on scaleEntry door fully openTruck confirmed on scale (axle sensors)Hold โ€” no door movement
STATE 3Entry door closingTruck on scale confirmedDoor closed and sealed (seal sensor)Weighing begins
STATE 4AIRLOCK HOLDEntry door sealedPressure equalized + weight captured + acceptance confirmedWeighing and pressure monitoring
STATE 5Exit door openingEntry door sealed + load acceptance approvedExit door fully open confirmedTruck exits to Dumping Floor
STATE 6Truck exitingExit door fully openTruck clear + dump body DOWN confirmedHold โ€” no door movement
STATE 7Exit door closing โ€” lane resetTruck clear + body DOWN confirmedExit door closed and sealedPrepare for next truck โ†’ STATE 0

6. Tipping Floor Operations

6.1 Truck Positioning and Bridge Raise Sequence

Truck enters Dumping Floor from TISAB exit door. SCADA LED signage displays assigned bay position.
Truck advances to assigned bay โ€” wheel guide rails prevent trough over-run. Truck stops โ€” wheel chock sensors confirm truck stationary.
Bridge interlock check (automatic): adjacent bridge DOWN confirmed, no personnel in proximity zone, truck stationary, hydraulic pressure nominal.
Hydraulic bridge raises to dump angle (45โ€“70ยฐ, 60ยฐ nominal) โ€” target <60 seconds.
Truck tips load โ€” Manufacturing Feedstock falls into trough. Bridge remains raised while tipping is active.
Truck raises dump body โ€” body-down sensor must confirm body DOWN and latched before bridge lower is permitted.
Bridge lowers โ€” target <60 seconds โ€” bridge confirmed DOWN and latched. Truck drives forward toward EASB.

6.2 Bridge Safety Interlock State Machine

StateNameEntry ConditionExit Condition
B0Bridge DOWN / LockedPower-up default or bridge lower confirmedRaise request + all interlocks clear
B1Interlock CheckRaise request receivedAll interlock conditions confirmed clear
B2Bridge RaisingAll interlocks clearedBridge at full dump angle confirmed
B3Bridge UP / Tipping ActiveBridge at dump angleTruck body DOWN + load complete + lower request
B4Bridge LoweringLower request + body DOWN confirmedBridge DOWN and latched confirmed
B5FAULT / LockedAny interlock violation or sensor faultSupervisor reset + fault cleared + manual confirmation. LOTO required for access.
Two-Bridge Operation Rule โ€” No Override
Only ONE bridge per trough may be raised at any time. This rule has no override. Raising both bridges on the same trough simultaneously is a hard interlock โ€” prohibited regardless of load conditions. Both troughs may be active simultaneously (e.g., Trough 1 Bridge A raising while Trough 2 Bridge B is lowering is permitted).

7. Trough 1 Operations โ€” Manufacturing Feedstock & Tires

7.1 Trough Level Response

Level ConditionActionNotification
HIGH (>80%)Pause Trough 1 truck intake โ€” hold new deliveriesAlert operations and dispatch
NORMAL (20โ€“80%)Normal operationNone required
LOW (<20%)Increase walking floor speed โ€” request additional truck routingAlert dispatch
LOW-LOW (<5%)Shredder Train notified of low feed โ€” prepare for feed interruptionAlert OPS-003 operator immediately

Tire Handling: Whole tires must be tipped at the designated tire bay only โ€” the first 50 ft of Trough 1 (solid-plate bridge section). Crumb rubber and pre-shredded tire material require no special handling and may be tipped at any Trough 1 bay.

APS Rule: If APS capture is lost, tipping operations for Trough 1 must stop immediately. No atmospheric venting is permitted under any operating condition.

8. Trough 2 Operations โ€” Sludge & Ash

8.1 NIR Moisture Routing Logic

NIR ReadingMaterial ClassPrimary RouteProcess Path
<15%AshBypass dryerLumpbreaker โ†’ Ash Pulverizer
15โ€“30%AshDryer trim cycleLumpbreaker โ†’ Ash Pulverizer
>30%AshFull dryer cycleLumpbreaker โ†’ Ash Pulverizer
<15%SludgeFlag anomalous โ€” supervisor reviewAsh Path (likely dried cake)
15โ€“60%SludgePre-dewatering โ†’ DryerSludge Pulverizer
>60%SludgePre-dewatering MANDATORYSludge Pulverizer

8.2 Leachate Management

ConditionActionNext Step
Normal levelSump pump AUTO โ€” no interventionLog volume per shift
HIGH alarmReduce sludge intake rate โ€” increase pump rateMonitor until HIGH cleared
HIGH-HIGH alarmStop Trough 2 intake immediatelySupervisor notification โ€” do not resume until sump capacity confirmed
โš  LOCKOUT / TAGOUT REQUIRED โ€” Trough 2 Wash-Down

LOTO required on Trough 2 walking floor and all Trough 2 feed conveyors before any personnel entry into the trough area for wash-down or maintenance.

Confirm zero energy state on all drives before entry. All wash water to leachate collection tank โ€” zero floor discharge.

Zero-discharge policy: no leachate, wash water, or centrate may be discharged to drain or ground under any condition.

9. EASB Exit Protocol

9.1 Normal Exit Sequence

Empty truck drives from Dumping Floor toward EASB. Traffic signal assigns Lane A or Lane B.
Entry door opens, truck advances onto EASB scale โ€” entry door closes and seals. AIRLOCK HOLD: 15-second pressure equalization.
Tare weight measured ยฑ20 lb and logged to SCADA.
SCADA tare reconciliation: EASB tare vs TISAB gross = net payload confirmed. Within ยฑ5% = ACCEPT. Outside tolerance = FLAG for supervisor review.
Exit door opens โ€” truck exits to public road. Exit door closes โ€” lane reset. Load record closed with full timestamps.

9.2 Reconciliation Discrepancy Protocol

ConditionSCADA ActionOperator Action
Within ยฑ5%ACCEPT โ€” record closed automaticallyNone required
Outside ยฑ5% (first occurrence)FLAG โ€” load record held open โ€” supervisor alertInvestigate cause โ€” document resolution
Scale drift suspectedFlag for calibration checkRemove scale from service pending calibration
Partial tip confirmedAdjust delivered tonnage in manifest recordDocument and notify dispatch

10. Negative Pressure Management

ZoneNormal SetpointAlarm LowAlarm HighAction if Out of Range
Dumping Floor (0B)โ€“0.05 to โ€“0.10 in. WCโ€“0.03 in. WCโ€“0.15 in. WCAlert APS โ€” adjust extraction rate
TISAB Airlock (0A)โ€“0.02 to โ€“0.05 in. WC (during hold)โ€“0.01 in. WCโ€“0.10 in. WCHold truck โ€” do not open exit door
EASB Airlock (0C)โ€“0.02 to โ€“0.05 in. WC (during hold)โ€“0.01 in. WCโ€“0.10 in. WCHold truck โ€” do not open exit door
Trough 1 (below floor)โ€“0.05 to โ€“0.10 in. WCโ€“0.03 in. WCโ€“0.15 in. WCAlert APS โ€” check Trough 1 APS damper
Trough 2 (below floor)โ€“0.05 to โ€“0.10 in. WCโ€“0.03 in. WCโ€“0.15 in. WCAlert APS โ€” check Trough 2 APS damper
Pressure Fault During Tipping โ€” Stop Tipping Immediately
If Dumping Floor or trough zone pressure rises above โ€“0.03 in. WC while any bridge is raised: (1) SCADA auto-issues bridge lower command. (2) Operator confirms bridge lower โ€” do not wait for auto-confirm. (3) Pause all truck tipping in affected zone. (4) Investigate APS fault before resuming. Do not resume tipping until APS confirmation that negative pressure is restored to setpoint.

11. Li-Battery & Energetic Material Protocol

11.1 Detection and Quarantine Sequence

Thermal camera triggers on object above 80ยฐC โ€” SCADA alert generated immediately.
Lift conveyor divert gate activates โ€” material routed to Quarantine Bay QA-01. Lift conveyor pauses.
Tipping operations for Trough 1 suspended until QA-01 inspection complete.
QA-01 water deluge activates automatically on temperature confirmation above 120ยฐC.
Operations supervisor notified immediately โ€” quarantine log entry created.
โš  QA-01 Entry Requirements โ€” Strict Compliance

No personnel may enter QA-01 until: CO concentration <25 ppm (confirmed by calibrated meter) AND temperature <40ยฐC.

LOTO required on water deluge system before personnel entry. Two-person minimum at all times in QA-01.

Full PPE including SCBA if CO or temperature cannot be confirmed prior to entry.

12. Startup Sequence โ€” Modules 0A/0B/0C

Startup Rule โ€” APS First, Always
Step 1 is mandatory and non-negotiable. No other equipment may be started until APS is confirmed running and negative pressure is confirmed in the Dumping Floor zone.
APS confirmed running and negative pressure confirmed (โ€“0.05 to โ€“0.10 in. WC). MANDATORY FIRST STEP โ€” do not proceed if failed.
EASB door controls enabled โ€” Lane A and Lane B.
Leachate sump pump set to AUTO.
Walking floors set to STANDBY โ€” Trough 1 and Trough 2.
Lift conveyors set to STANDBY.
Trough 2 feed conveyors set to STANDBY.
Bridge hydraulic power units ON โ€” pressure confirmed on SCADA.
Bridge controls enabled โ€” all bridges confirmed DOWN and latched on position sensors.
Thermal detection camera confirmed active.
Dumping Floor LED bay assignment system active โ€” test display cycle.
Module 0A/0B/0C READY: Notify TISAB to begin truck intake. Notify OPS-003 (Shredder Train) and OPS-004 (Trough 2 Processing).

13. Shutdown Sequence

Shutdown Rule โ€” APS Last, Always
The APS must remain running until all material has been cleared from the Dumping Floor building and all enclosures are sealed. Do not shut down APS while any trough, bridge, or conveyor is active.
Notify dispatch: no new truck assignments. Allow in-transit trucks to complete their cycle.
Stop Trough 1 and Trough 2 walking floors after last truck completes tipping.
Allow lift conveyors to run until material clear โ€” confirm empty by level sensor and visual.
Stop lift conveyors. Stop Trough 2 feed conveyors.
Lower all bridges โ€” confirm DOWN and latched on all position sensors.
Bridge HPUs OFF after bridges confirmed down.
Leachate sump pump to MANUAL โ€” confirm sump pumped down before shutdown.
Door controls disabled โ€” all doors confirmed closed and sealed.
APS shutdown only after building fully sealed and all equipment stopped. Notify APS operator โ€” coordinate APS shutdown timing.

14. Emergency Procedures

EmergencyImmediate ActionSCADA ActionEscalation
Fire in Dumping Floor buildingActivate building E-stop pull cord โ€” all doors hold. Evacuate building immediately. Muster point per site plan.All doors freeze in current position. APS continues. NFPA suppression activates.Emergency services. Facility emergency coordinator.
Li-battery thermal event at troughActivate nearest E-stop. Do not approach. Move to muster point.Divert gate to QA-01. Water deluge auto-activates above 120ยฐC.Emergency coordinator. Fire brigade. QA-01 protocol Section 11.
APS pressure loss during tippingStop tipping โ€” lower bridge immediately per Section 10.3.Auto-lower command issued. Alarm logged.APS operator. Operations supervisor.
Bridge stuck in raised positionStop all tipping operations. Do not attempt manual lowering without LOTO.Fault state B5. All further bridge raises locked.Maintenance LOTO procedure. Engineering on call.
Person under raised bridgeActivate nearest E-stop immediately. Bridge holds in current position.E-stop logged. All bridge motion locked.Emergency services immediately. Do not lower bridge until personnel confirmed clear.

15. Performance KPIs

KPITargetAlarm ThresholdMeasurement Basis
Truck processing rate>30 trucks/hr per lane<25 trucks/hr sustainedSCADA load records per shift
Airlock cycle time<3 minutes per truck>5 minutes sustainedSCADA door state timestamps
Payload reconciliation accuracyโ‰ฅ98% of loads within ยฑ5%<95% in any shiftSCADA reconciliation log per shift
Bridge raise/lower cycle<60 seconds each direction>90 secondsSCADA bridge state timestamps
Dumping Floor negative pressureโ€“0.05 to โ€“0.10 in. WC at all timesAbove โ€“0.03 in. WC for >30 secContinuous SCADA pressure monitoring
Leachate zero discharge compliance100% โ€” zero discharge eventsAny discharge eventLeachate tank level and pump logs
Li-battery quarantine response time<60 seconds from detection to divert>90 secondsSCADA thermal camera alarm to divert gate confirmation
END OF DOCUMENT โ€” CBT-PRE-OPS-002 | Rev 0 | April 2026 | CONTROLLED โ€” CARBOTURA INC.
Pregenesis Protocol Operations | Modules 0A / 0B / 0C | Governed by CBT-PRE-OPS-001 Master Protocol