Carbotura
Engineering Portal
Confidential
Pregenesis Protocol β€” Technical Design Specification

Modules 0A, 0B & 0C
Truck Intake & Scale Airlock, Dumping Floor & Trough System, Exit Airlock Scale Building

Complete feedstock reception system β€” TISAB, Dumping Floor, dual troughs, EASB

Doc No.CBT-PRE-TDS-002
RevisionRev 1
OER ClassClass 2 Β±15%
DateApril 2026
ClassificationConfidential
RevCon BaselineRevCon 3
Document Control
Document NumberCBT-PRE-TDS-002
RevisionRev 1 β€” April 2026
OER ClassificationClass 2 (Β±15%) OEM Engineering Release β€” equivalent to "FEED / DOE FEL-3" [external regulatory reference β€” DOE LPO / AACE 18R-97 only]
StatusIssued for Review β€” PE Sign-Off / Investor Bill of Sale
OwnerCarbotura Inc. β€” Engineering
Quality StandardISO 9001:2015
Authorized Strategic Integrator (ASI)Role open to qualified ASI candidates per CBT-ASI-QUAL-001. RK Industries previously referenced β€” designation pending final partnership execution.
RevCon Performance BaselineRevCon 3 β€” $150M–$325M/yr revenue floor, 400 TPD baseline factory
ChairmanAllen Witters
Revision History
RevDateAuthorDescription
0April 2026Carbotura EngineeringInitial Issue β€” Class 4 Preliminary (Β±30%). All ICDs status TBD.
1April 2026Lead Systems Architect / OEM Engineering DirectorClass 2 OER Upgrade. All ICD entries resolved per CBT-PRE-ICD-001 Rev 1. ASI terminology applied. Terminology Firewall v1.0 enforced. Skid-Integrated Spring Isolation references added via ICD package. RevCon 3 performance baseline confirmed.

1. Executive Summary

DIAG-PRE-001 Pregenesis Protocol β€” Material Flow Overview
Process Flow
Module 0A Β· TISAB
Truck Arrival
RFID + Manifest
↓
NTEP Weighbridge
Gross Weight Β±20 lb
↓
Airlock Hold
15 sec Β· βˆ’0.02 in. WC
β†’
Module 0B Β· Dumping Floor
Bay Assignment
LED Signage
↓
Hydraulic Bridge
45–70Β° Raise
↓
Trough 1
MSW + Tires
↓
Trough 2
Sludge + Ash
β†’
Shredder Train Β· Modules 1–4
Tire Pre-Shredder
↓
Primary Shredder
SHRD-SHR-001/002 Β· 380 kW
↓
MFS Stage 1
Bulk Ferrous β†’ FCB-001/002
↓
Hammermill
P80 ≀25 mm
↓
MFS Stage 2
Fine Wire β†’ FCB-003/004
↓
Rotational Mixer
AFR = 0.25 Β· CV <5%
↓
Regenesis Feed Bin
β†’
Output
To Regenesis MCR
Blended Β· AFR 0.25 confirmed
T2 Processing Β· Ash Path
NIR Moisture Sensor
Routing decision
↓
Lumpbreaker
↓
VRM Pulverizer
P80 <500 Β΅m Β· ATEX Z21
↓
Ash Silo
ASL-001/002
↑ feeds Rotational Mixer
Also: Module 0C Β· EASB β€” Tare weight confirmation Β±5% Β· Load record close
Material flow from truck arrival through Pregenesis preparation to Regenesis MCR feed. APS Capture Stream runs parallel to all enclosed process zones (not shown for clarity).
DIAG-PRE-002 TISAB / EASB Airlock β€” 8-State Door Interlock Machine
State Machine
[*] Power Up
Raise request + interlocks clear
S0 β€” Both Doors Closed
Standby
Raise request + interlocks clear
S1 β€” Entry Door Opening
Entry door fully open
S2 β€” Truck Entering Β· On Scale
Truck on scale confirmed
S3 β€” Entry Door Closing
Entry door sealed
S4 β€” AIRLOCK HOLD
βˆ’0.02 to βˆ’0.05 in. WC Β· NTEP weight captured Β· Load acceptance confirmed
Weight captured + acceptance confirmed
S5 β€” Exit Door Opening
Exit door fully open
S6 β€” Truck Exiting Floor
Truck clear + dump body down
S7 β€” Exit Door Closing Β· Lane Reset
Exit door sealed β†’ return to S0
↩
State machine governs both Lane A and Lane B independently. No door movement permitted outside this logic. STATE 4 (Airlock Hold) is the only state where negative pressure equalization and weighing occur.
Document Boundary Statement
This Technical Design Specification defines module-level technical requirements, interfaces, testing, and warranty boundaries only; commercial risk allocation, financing structures, delivery arrangements, and lender requirements are addressed in separate contractual and financing documents.
Manufacturing Classification Statement
This Technical Design Specification describes module-level requirements for an Advanced Circular Manufacturing subsystem and does not define or imply waste treatment, storage, or disposal activities.
Near-Zero Design Intent
The Pregenesis intake system is engineered as a closed-loop manufacturing subsystem designed for near-zero emissions, near-zero discharge, and near-zero residual. This design intent is achieved through enclosed material handling, continuous negative-pressure operation, internal capture of all airborne particulates and vapors via the APS Capture Stream, and the absence of routine wastewater discharge or disposal pathways. Environmental performance outcomes are contingent on execution at commercial scale and will be validated through SAT and FPT procedures.

This TDS defines the engineering requirements for the Pregenesis feedstock intake, receiving, and trough feed system. It covers Manufacturing Feedstock reception through the Truck Intake & Scale Airlock Building (TISAB β€” Module 0A), feedstock receiving on the Dumping Floor (Module 0B) with dual-trough material routing, and truck exit through the Exit Airlock Scale Building (EASB β€” Module 0C). Trough 2 walking floor connection to the T2 processing train (Module T2, detail in CBT-PRE-TDS-004) is also defined within this document boundary.

Together, Modules 0A, 0B, and 0C constitute the complete feedstock reception system upstream of the Pregenesis Shredder Train (CBT-PRE-TDS-003). The system is designed for 1,000 TPD (as-received) per trough, with full N+1 redundancy on all walking floor and conveyor equipment. Both troughs operate independently at full 1,000 TPD nameplate capacity. The TISAB and EASB buildings provide a 4-hour surge buffer at design throughput.

All three modules maintain a continuous negative-pressure boundary (–0.05 to –0.10 in. WC throughout the Dumping Floor; –0.02 to –0.05 in. WC at TISAB/EASB airlocks), ensuring air flows inward from atmosphere at all times. No routine atmospheric discharge occurs from any module in this group. The Atmospheric Protection System (APS) recovers all airborne particulates and vapors as product streams per CBT-APS-TDS-001.

2. Facility Context & Module Boundaries

2.1 Module Position in Facility

Modules 0A, 0B, and 0C form the front-end of the Pregenesis Protocol. TISAB (0A) is the entry pressure boundary; the Dumping Floor (0B) is the central receiving area with dual troughs; EASB (0C) is the exit pressure boundary. All three modules maintain a continuous negative-pressure boundary ensuring air flows inward from atmosphere at all times.

BoundaryDescriptionReference
UpstreamFacility perimeter / public road (truck arrival)N/A β€” facility boundary
Downstream (Trough 1)Lift conveyor discharge to Primary Shredder feed hopperCBT-PRE-TDS-003
Downstream (Trough 2)Walking floor discharge to Trough 2 Processing trainCBT-PRE-TDS-004
Excluded: Shredder TrainModules 1–6 size reduction, ferrous separation, blendingCBT-PRE-TDS-003
Excluded: T2 ProcessingTrough 2 thermal drying and pulverizing to <500 Β΅mCBT-PRE-TDS-004
Excluded: APS SystemAPS design (fans, filters, ducts, product recovery)CBT-APS-TDS-001

2.2 Input Register

Input StreamSourceRoutingNotes
Manufacturing Feedstock (MSW / tires)Inbound trucks via TISABTrough 1Primary Pregenesis Manufacturing Feedstock stream
Sludge / ashInbound trucks via TISABTrough 2Sludge and ash to T2 Processing
Electrical powerSite utility / 32 MW PowerBlockAll modules480V 3-phase 60 Hz; main service 4,160V or 13.8 kV
Compressed airSite compressorsAll modules100 psig β€” door actuators, instruments, controls
SCADA facility management signalFacility SCADA masterAll modulesBay assignment, throughput demand, payload reconciliation

2.3 Output Register

Output StreamDestinationRateNotes
Shredded feedstock to Shredder TrainTrough 1 lift conveyor to Primary Shredder~985–995 TPDAfter magnetic head pulley ferrous removal
Ash/sludge stream to T2 ProcessingTrough 2 walking floor to T2 train1,000 TPDLeachate accounted separately
Ferrous metalsFerrous collection bin~0.5–1.5% of Trough 1 flowMagnetic head pulley on Trough 1 lift conveyor
APS Capture Streams (all enclosures)APS (CBT-APS-TDS-001)~2,200 CFM normalProcess-capture basis; no dilution air
LeachateWater treatment moduleVariableTrough 2 sump β€” designed for near-zero discharge
Confirmed payload data (SCADA)Facility SCADA / billing systemPer truckTISAB gross vs EASB tare reconciliation

3. Process Description

3.1 Narrative Overview

Trucks arrive at the TISAB, pass through a two-lane airlock with certified weighbridge, tip their loads on the Dumping Floor, and exit via the EASB mirror airlock. The TISAB/EASB airlock system maintains the facility negative pressure boundary at all times β€” air always flows inward from atmosphere. The airlock interlock prevents both the entry and exit doors of any lane from being simultaneously open, preserving the pressure differential. RFID transponder readers at TISAB entry capture truck identification and are matched to EASB tare weight for payload reconciliation.

The Dumping Floor contains two parallel troughs running lengthwise. Trough 1 receives Manufacturing Feedstock (MSW and tires); hydraulic drawbridges raise to allow tipping directly into the trough. A walking floor system at the trough base meters material to a lift conveyor feeding the Shredder Train. Trough 2 receives sludge and ash with identical architecture routing to the Trough 2 Processing train. Bay assignment via SCADA LED signage routes each truck to the correct trough based on load manifest data.

3.2 Process Flow

StepModuleActionKey Parameter
1TISABTruck arrives β€” RFID tag read at lane entryEPC tag capture
2TISABAirlock hold β€” pressure equalization–0.02 to –0.05 in. WC vs. outside
3TISABWeighbridge measures gross weightΒ±20 lb legal-for-trade (NTEP)
4TISABExit door opens, truck enters Dumping FloorSCADA bay assignment signal
5Dumping FloorBay assignment via LED signage β€” Trough 1 or 2Load manifest match confirmed
6Dumping FloorHydraulic bridge raises<60 sec raise cycle
7Dumping FloorTruck tips Manufacturing Feedstock into troughGravity discharge; all material confined to trough
8Dumping FloorBridge lowers; truck proceeds to EASB<60 sec lower cycle
9EASBAirlock hold β€” pressure equalization–0.02 to –0.05 in. WC vs. outside
10EASBTare weight confirmedΒ±20 lb legal-for-trade
11EASBPayload reconciliation (gross – tare = net)Β±5% reconciliation tolerance
12EASBTruck exits β€” RFID load record closedLoad record archived to SCADA

3.3 Mass Balance

StreamTroughDesign Rate (TPD)Notes
MSW + tires inputTrough 1Up to 1,000P90 envelope includes 100% tires by day
Sludge + ash inputTrough 2Up to 1,000Moisture 60–85% sludge; 5–30% ash
Output to Shredder TrainTrough 1 lift conveyor~985–995After magnetic head pulley ferrous removal (~0.5–1.5%)
Output to T2 ProcessingTrough 2 walking floor1,000Leachate volume accounted separately in T2 mass balance
Ferrous metals removedTrough 1 magnetic head pulley~5–15Estimated 0.5–1.5% of MSW+tire stream; co-manufactured revenue stream
Total system input (combined)Both troughsUp to 2,000Full dual-trough design capacity

3.4 Key Process Parameters

ParameterValueBasis
Building negative pressure–0.05 to –0.10 in. WCRelative to TISAB/EASB interior
TISAB/EASB pressure–0.02 to –0.05 in. WCRelative to outside atmosphere
Airlock cycle time target<3 minutes per truckDoor close + verify + door open sequence
Trough 1 capacity (design)1,000 TPDMSW + tire Manufacturing Feedstock
Trough 2 capacity (design)1,000 TPDSludge + ash streams
Drawbridge raise/lower cycle<60 secondsFull travel; hydraulic drive
Surge buffer (trough)4-hour supply at design throughput~167 tons at 1,000 TPD
Walking floor speed0–12 ft/min variableSCADA-controlled via proportional hydraulic valve
Payload reconciliation toleranceΒ±5%TISAB gross vs EASB tare; pass/fail threshold
Truck throughput (design)60+ trucks/hour per direction2 lanes Γ— 30 trucks/hr per lane

4. Feedstock Design Envelope

Guarantee Conditionality
All throughput and equipment performance guarantees apply when Manufacturing Feedstock is within the P90 design envelope defined below, utilities are provided at specification, and operators follow OPS procedures. Any Li-battery detection in an inbound load triggers immediate quarantine; no-tip protocol applies until visual inspection clears the load.

4.1 Trough 1 β€” MSW & Tire Feedstock Design Envelope

ComponentP50 Range (wt%)P90 Design Max (wt%)Design Consideration
Paper / Cardboard20–28%35%High cellulose; manageable via walking floor
Plastics (mixed)12–18%22%Mixed polymers; no special handling required
Food organics20–35%42%High moisture; contained by negative pressure + APS
Yard waste5–15%20%Seasonal variation; lignocellulosic bulk
Ferrous metals3–6%8%Recovered at magnetic head pulley on lift conveyor
Non-ferrous metals1–3%4%Pass-through to Shredder Train
Glass / ceramics3–6%8%Inert; manageable with AR400-lined trough
Textiles / Rubber2–6%10%Rope/textiles can bridge β€” walking floor handles
Whole tires0–10%40%Bridge-tip directly; tires 100% by day acceptable
Li-ion batteriesTraceANY DETECTIONQuarantine protocol β€” thermal camera required at TISAB approach

4.2 Prohibited Materials

MaterialHazardDetection MethodProtocol
Li-ion / Li-polymer batteriesThermal runaway / fireFixed thermal camera at truck approachQuarantine bay β€” load rejected before tipping
Pressurized cylinders (any gas)ExplosionVisual inspection + operator notificationReject at gate; do not permit entry
Radioactive materialsRadiationFixed portal radiation detector at TISAB entryImmediate quarantine; emergency protocol
Liquid in bulk containersLeachate, fireVisual + RFID manifest checkReject at gate unless classified as approved sludge stream
Medical / sharps wasteBiohazardManifest reviewReject β€” not accepted as Manufacturing Feedstock

5. Module Equipment Specifications

5.1 TISAB β€” Truck Intake & Scale Airlock Building TISB-BLD-001/002

TISAB β€” Truck Intake & Scale Airlock Building TISB-BLD-001/002
Building Type
Sprung Structure fabric building on reinforced concrete slab
Configuration
2 parallel drive-through lanes, fully enclosed
Lane Dimensions
18 ft wide Γ— 90 ft long per lane
Total TISAB Footprint
~50 ft Γ— 100 ft (including wall thickness and service access)
Ceiling Height (clear)
22 ft minimum β€” accommodates loaded semi-trailer clearance
Doors Per Lane
2Γ— automatic high-speed insulated roll-up doors (4 doors total)
Door Dimensions
16 ft W Γ— 16 ft H clear opening per door
Door Cycle Rating
Minimum 50,000 cycles/year
Door Interlock
Entry door must fully close and seal before exit door opens β€” true airlock sequence
Weighbridge Type
In-ground certified legal-for-trade weighbridge, pit-mount, per NIST Handbook 44
Weighbridge Capacity
100,000 lb (legal-for-trade NTEP certified)
Weighbridge Accuracy
Β±20 lb
Weighbridge Platform
70 ft L Γ— 11 ft W per lane β€” full semi-trailer wheelbase
RFID/Transponder
Passive UHF RFID readers at lane entry β€” industrial weatherproof grade
Airlock Cycle Time
<3 minutes per truck (door close + verification + door open)
Pressure Differential
–0.02 to –0.05 in. WC relative to outside atmosphere
APS Capture (Normal)
400 CFM β€” process-capture basis; no dilution air
APS Capture (Peak)
700 CFM β€” during peak truck traffic and door cycling
Estimated CAPEX
$800K–$1.5M per building [Class 2 Β±15%]

5.2 Trough 1 β€” MSW & Tires DUMP-TR1-001

Trough 1 β€” MSW & Tire Manufacturing Feedstock DUMP-TR1-001
Function
Receive MSW and tire Manufacturing Feedstock; meter to Shredder Train via lift conveyor
Dimensions
12 ft wide Γ— 200 ft long Γ— 16 ft deep (clear inside)
Surge Buffer (design)
4-hour supply at 1,000 TPD = ~167 tons at 425 lb/ydΒ³ average MSW density
Wall Liner
AR400 abrasion-resistant steel plates, 3/8-in. thick, bolt-on replaceable panels
Walking Floor Type
Reciprocating slat walking floor conveyor (hydraulic drive)
Walking Floor Qty
2 units at 50% duty cycle β€” each rated 1,000 TPD full throughput
Walking Floor Speed
0–12 ft/min variable, SCADA-controlled via proportional hydraulic valve
Lift Conveyor Type
2Γ— enclosed belt conveyor, fire-resistant NFPA rated, heavy-duty chevron/cleated belt
Lift Conveyor Capacity
1,000 TPD per unit; 1,500 TPD surge capacity
Lift Conveyor Inclination
18–22 degrees
Magnetic Head Pulley
Rare-earth permanent magnet; continuous ferrous removal at conveyor discharge; est. 0.5–1.5% of stream

5.3 Hydraulic Drawbridge System DUMP-HDB-xxx

Hydraulic Drawbridge System β€” Both Troughs DUMP-HDB-xxx
Quantity
2 hydraulic lift bridges per trough (4 total)
Load Rating
80,000 lb GVW minimum; 100,000 lb design load
Structural Frame
W-section steel beams, galvanized; designed per AASHTO HL-93 + 25% dynamic factor
Raise/Lower Cycle
<60 seconds full travel
Safety β€” Wheel Chock
Pneumatic/electronic wheel chock engagement confirmed before bridge raise initiates
Safety β€” Personnel
Laser curtain / photo-eye array confirms no personnel beneath bridge β€” Class IV per ANSI/NFPA 79
Emergency Stop
E-stop pull cords both sides of each bridge; mushroom-head E-stop at each HPU; SCADA alarm logged
Estimated CAPEX
$300K–$600K per pair (2 bridges per trough) β€” custom fabrication; performance-specified [Class 2 Β±15%]

6. APS Interface Register

APS Process-Capture Basis Statement
CFM figures are process-capture basis only. No dilution air, comfort ventilation, or regulatory dispersion airflow is included. All APS Capture Stream flows represent product streams being recovered or contaminated air managed internally. APS system design is specified in CBT-APS-TDS-001.
ModuleAPS Capture PointNormal CFMPeak CFMTemp (Β°C)MaterialRecovery Value
TISAB (0A)Ceiling duct β€” building400700AmbientCoarse particulate, minor biogasCarbon fines to recovery
Trough 1 (0B)Open-top duct pickup6001,000Ambient–35MSW particulate, biogas traces, rubber dustCarbon fines; biogas to APS recovery
Trough 2 (0B)Open-top duct pickup500900Ambient–45Sludge vapors, ash particulate, Hβ‚‚SCondensate to water treatment; dry fines to recovery
Dumping Floor generalBuilding envelope ceiling plenum300500AmbientGeneral building air, minor fugitive particulateGeneral containment
EASB (0C)Ceiling duct β€” building400700AmbientCoarse particulate, minor biogas from empty trucksCarbon fines to recovery
TOTAL β€” 0A/0B/0CAll capture points combined~2,200~3,800β€”Combined process-capture streamPer individual stream above

7. Modular Installability & Interface Control

All Pregenesis sub-modules are delivered as factory-assembled, pre-wired, and pre-tested units designed for Modular Assembly upon delivery. Field activities are limited to module placement, standardized mechanical and electrical interconnections, and verification testing per SAT and FPT procedures. All interfaces use RK Industries ASI Standardized Connectors per CBT-PRE-ICD-001 Rev 1.

ICD Rev 1 β€” Zero TBD Entries
All six ICD entries for Modules 0A/0B/0C have been fully resolved in CBT-PRE-ICD-001 Rev 1. Interface Readiness Level (IRL) upgraded from IRL 3–4 (Rev 0) to IRL 5 (Rev 1). See the full ICD document: CBT-PRE-ICD-001 Rev 1 β†’
InterfaceICD ReferenceConnection TypeStatus
TISAB entry β†’ Dumping FloorICD-TISB-DUMP-001Pressure boundary door + APS duct + Modbus TCP dataDEFINED β€” Rev 1
Dumping Floor β†’ EASBICD-DUMP-EASB-001Pressure boundary door + APS duct + Modbus TCP dataDEFINED β€” Rev 1
Trough 1 lift conveyor β†’ Shredder TrainICD-DUMP-SHRD-001Flanged AR400 chute + E-stop SIL 1 + Modbus TCP feed rateDEFINED β€” Rev 1
Trough 2 feed conveyor β†’ T2 ProcessingICD-DUMP-T2PR-001Flanged 316L SS chute + NIR analog + Modbus TCP routingDEFINED β€” Rev 1
All modules β†’ APSICD-DUMP-APS-0015Γ— ASI-APS-FLG-6IN-RD + Rosemount 3051 DP + Modbus TCPDEFINED β€” Rev 1
TISAB/EASB β†’ SCADA MasterICD-TISB-SCADA-001Full Modbus TCP/IP I/O marshaling β€” weighbridge, RFID, doors, bay LEDDEFINED β€” Rev 1
SAT / FPT Statement
Site Acceptance Testing (SAT) and Full Performance Testing (FPT) will be conducted following module assembly and initial startup. A 72-hour continuous Throughput Performance Guarantee Test (TPGT) is required with Manufacturing Feedstock within the P90 envelope, witnessed by Carbotura Engineering, Owner's Engineer, and an independent third party.

8. Utilities Register

8.1 Electrical Load Schedule

Sub-ModuleEquipmentNormal Load (kW)Peak Load (kW)Notes
TISAB (0A)Doors, scales, RFID, lighting, controls3560Primarily door motors and weighbridge controllers
Dumping Floor (0B)Walking floors (2Γ— T1 + 2Γ— T2)120240Walking floor HPU drives scale with throughput
Dumping Floor (0B)Lift conveyors (2Γ— Trough 1)801602Γ— 75 HP VFD motors at 50% duty
Dumping Floor (0B)Bridge HPUs (4 sets)4080Intermittent; 50 HP each during bridge cycle
Dumping Floor (0B)Signage, lighting, controls, leachate pumps2540LED lighting, SCADA controls, sump pumps
EASB (0C)Doors, scales, RFID, lighting, controls3560Mirror of TISAB electrical load
TOTAL β€” 0A/0B/0CAll sub-modules combined~335 kW~580 kWAt 1,000 TPD design throughput

9. Vendor Matrix

9.1 Sprung Structure Buildings

VendorCountryOEM GuaranteeKey SpecsNotes
Sprung Structures Inc.Canada / USAYes β€” 10 yr structure, 5 yr fabricClear-span, automated roll-up doors, negative pressure capable, 22+ ft clearanceIndustry leader; extensive industrial reference installations
ClearSpan Fabric StructuresUSAYes β€” 50 yr structuralCustom clear-span, full-height roll-up doors, insulated fabricStrong North American presence
Legacy Building SolutionsUSAConfirm at RFQRigid frame clear-span, high-bay rated, custom door configurationsSteel rigid frame with fabric skin; heavy-duty industrial

9.2 Truck Weighbridges

VendorCountryOEM GuaranteeKey SpecsNotes
Mettler ToledoUSA / GlobalYes β€” 24 months parts + laborLegal-for-trade, NTEP certified, pit-mount, SCADA integrationGlobal standard; full service network
Rice Lake Weighing SystemsUSAYes β€” 24 monthsFull range pit-mount legal-for-trade; SCADA integrationStrong USA dealer network; competitive pricing
Avery Weigh-TronixUSA / UKYes β€” 24 monthsOIML/NTEP dual-certified, pit-mount, SCADA/ERP readyGlobal network; strong in regulated industrial applications

10. CAPEX Estimate

AACE Classification β€” Class 2 (Β±15%) | 2026 USD
This capital cost estimate is classified as Class 2 (Β±15%) OEM Engineering Release per AACE International RP 18R-97. All values in 2026 USD. Estimating methodology: factored/parametric β€” equipment costs from budget quotes, ROM quotes, and industry benchmarks.
Line ItemLow EstimateHigh EstimateBasis
TISAB building (Sprung Structure + fitout)$600K$1.2MSprung structure + doors + slab + fire suppression
TISAB scales + weighbridge systems (2 lanes)$120K$250K2Γ— NTEP-certified pit-mount scales + controllers
TISAB doors + controls + RFID$80K$150K4 doors, PLC interlocks, RFID readers, safety systems
Dumping Floor concrete Modular Assembly$800K$1.5MReinforced slab + push walls + floor drains
Trough 1 + AR400 liner$400K$800KRC walls, AR400 steel liner panels, wheel guides
Trough 1 hydraulic bridges (2 sets)$600K$1.2MCustom fabrication; AASHTO HL-93 rated; HPUs included
Trough 1 walking floors (2Γ—) + lift conveyors (2Γ—) + magnetic head pulley$700K$1.4MKeith or equivalent; AR400 slats; hydraulic drive; enclosed belt NFPA
Trough 2 + 316L liner + sump$500K$1.0MRC walls, 316L SS liner, leachate sump + tank + pumps
Trough 2 hydraulic bridges (2 sets)$600K$1.2MSame as Trough 1 + corrosion upgrades
Trough 2 walking floors (2Γ—, 316L) + feed conveyors (2Γ—)$550K$1.1M316L SS slats + corrosion premium; screw/en-masse conveyors
EASB building + scales (mirror of TISAB)$700K$1.4MSame spec as TISAB; 2 lanes, 4 doors, 2 scales, RFID
Thermal cameras + Li-battery detection$80K$150KFixed thermal cameras at TISAB approach; SCADA integration
Subtotal β€” Direct Equipment$5.73M$11.35MLines above
Electrical, instrumentation, controls (15%)$860K$1.7ME&I at 15% of equipment subtotal β€” Class 2 basis
Modular Assembly labor (15%)$860K$1.7MASI assembly at 15% of equipment subtotal
Contingency (15%)$1.12M$2.21MApplied per AACE Class 2 basis
TOTAL CAPEX β€” Modules 0A/0B/0C$8.57M$16.96MClass 2 Β±15% | AACE 18R-97 | 2026 USD

13. TRL / ERL / IRL Assessment

Equipment / SystemTRLERLIRLAssessment Notes
Sprung Structure buildings955Fully commercial; deployed at hundreds of industrial sites (Sprung/ClearSpan OEM data)
Certified truck weighbridges955Mature commercial technology; NTEP certification established standard
Reinforced concrete trough955Standard civil/structural; no novel technology
Walking floor systems955Established technology; 40+ year heritage in bulk solids (Keith Manufacturing operating records)
Hydraulic drawbridges7–844Custom adaptation of proven hydraulic bridge technology; performance-spec procurement; limited tipping floor reference
Lift conveyors + magnetic head pulley955Standard industrial belt conveyor; magnetic head pulley proven for ferrous separation
TISAB/EASB integrated airlock + pressure management6–73–45Novel integration of proven airlock and pressure control technologies; IRL upgraded to 5 in Rev 1 with full ICD definition
SCADA payload reconciliation845Weighbridge SCADA integration well-established; automated net payload reconciliation standard in WTE applications
OVERALL MODULE TRL745IRL upgraded Rev 0β†’Rev 1 with full ICD definition

14. Confidence Factor

FactorWeightScore (0–10)Weighted ScoreRationale
Technology maturity (TRL)25%8.52.13Most equipment TRL 9; hydraulic bridges TRL 7–8; integrated airlock TRL 6–7
Engineering completeness (ERL)20%8.01.60ERL 4–5 on established equipment; Class 2 OER achieved Rev 1
Integration readiness (IRL)15%9.01.35All ICDs fully defined Rev 1; IRL upgraded to 5
Vendor availability & supply chain15%8.51.28Multiple qualified vendors for all categories
Operational heritage15%7.51.13Walking floors/conveyors well-referenced; integrated negative-pressure airlock facility is novel combination
Regulatory / permitting clarity10%7.50.75No novel regulatory pathway for standard equipment; facility-level permitting is site-specific
TOTAL CONFIDENCE SCORE100%β€”8.24 / 10 = 82.4%GOOD β€” Investor-bankable at Rev 1 Class 2 OER

15. Availability Model

EquipmentMAMTBF (hr)MTTR (hr)Notes
TISAB/EASB roll-up doors>98%>5,0001–22N redundancy; door motor replacement is maintenance task (OEM operating records)
Truck weighbridges>99%>10,0001Highly reliable; load cell replacement if needed is fast (Mettler Toledo OEM data)
RFID reader systems>99.5%>15,000<1Solid-state; spare units on site
Hydraulic drawbridges92–95%1,000–2,0002–4Custom hydraulic system; cylinder seal wear primary failure mode; critical path for system OA (calculated β€” industry hydraulic cylinder benchmark)
Walking floor systems94–97%2,000–4,0002–450% duty cycle on 2Γ— units; slat replacement is planned maintenance (Keith Manufacturing reference data)
Lift conveyors (Trough 1)96–99%3,000–6,0001–350% duty cycle; belt and magnetic head pulley are planned maintenance items
Feed conveyors (Trough 2)95–98%2,500–5,0001–3316L SS screw conveyor; bearing and seal service in corrosive sludge environment
System OA β€” 0A/0B/0C~93%β€”β€”Dominated by hydraulic bridge MA; N+1 walking floor/conveyor provides headroom. P50 throughput: 930 TPD avg.

16. Risk Register

Risk IDCategorySeverityMitigation
R-01Hydraulic bridge custom fabrication β€” schedule riskMEDIUMCritical path at 20–32 weeks. Early procurement decision. ICD finalization before fabrication release. Dual-source HPU components.
R-02Trough 2 sludge leachate β€” near-zero discharge complianceMEDIUM316L SS liner + sump design. Duplex leachate pumps. Leachate tank sized for 4-hour peak. Route to water treatment at all times.
R-03Li-battery or pressurized container in Manufacturing Feedstock β€” fire risk at tippingHIGHThermal cameras at TISAB approach for truck load screening. Quarantine bay protocol. Load rejection before tipping confirmed. NFPA fire suppression throughout building.
R-04Payload reconciliation discrepancy (>5%) β€” operational data qualityLOWRegular NTEP re-certification annually. SCADA automated reconciliation with flagging. Manual override protocol for out-of-tolerance loads.
R-05NIR sensor accuracy for Trough 2 moisture routingMEDIUMDual NIR sensors with cross-validation. Manual override available. SCADA trending to track sensor calibration drift.
R-06High-moisture sludge causing Trough 2 walking floor slippageMEDIUM316L SS slat material. Ribbon-flight screw conveyor for cohesive sludge. SCADA alarm on low conveyor speed vs. demand.
R-07Pressure boundary loss (TISAB or EASB door failure)MEDIUMRedundant door interlocks. Pressure monitoring with SCADA alarm at –0.01 in. WC threshold. Automatic APS fan speed increase on pressure drop.

18. Warranty Register

Guarantee Conditionality Statement
All throughput, performance, and availability guarantees apply when: (1) Manufacturing Feedstock is within the P90 design envelope defined in Section 4; (2) utilities are provided at specification per Section 8; (3) operation follows OPS procedures; (4) Planned Maintenance Intervals are adhered to; and (5) the Authorized Strategic Integrator (ASI) has completed Factory Acceptance Testing and issued the Unitized Warranty Passport.
EquipmentVendorWarranty PeriodCoverageNotes
Sprung Structure buildingsSprung / ClearSpan / Legacy10 yr structure, 5 yr fabricStructural frame and fabric coveringDoor warranty is separate sub-contract with door OEM
Certified truck weighbridgesMettler Toledo / Rice Lake / Avery24 months parts + laborLoad cells, summing box, controller, wiring harnessNTEP re-certification required annually regardless of warranty status
Walking floor systemsKeith / Hallco / Cargo Floor18 monthsSlats, hydraulic cylinders, drive frame, control valvesSlat wear is a consumable β€” warranty covers manufacturing defects, not normal wear
Hydraulic drawbridgesCustom structural fabricator (ASI-qualified)24 monthsStructural frame, hydraulic cylinders, HPUs, safety interlocksPerformance against spec must be verified at SAT
Lift conveyorsSuperior / Fenner / Continental18 monthsBelt, drive system, structural frame, magnetic head pulleyBelt warranty covers defects; wear from abrasive MSW is operational consumable
Feed conveyors β€” Trough 2Custom 316L SS fabricator (ASI-qualified)18 months316L SS screw flights, trough, bearings, seals, VFD drivesCorrosion warranty requires feedstock within Trough 2 design envelope
END OF DOCUMENT β€” CBT-PRE-TDS-002 | Rev 1 | April 2026 | CONFIDENTIAL β€” CARBOTURA INC. β€” ALL RIGHTS RESERVED
RevCon 3 Performance Baseline | Authorized Strategic Integrator (ASI) Integration Model | Class 2 OER Β±15%