Modules 1–4: Primary Shredding, Hammermill,
Ash Pulverizer & Rotational Mixer
Pregenesis Shredder Train — complete size reduction, ferrous separation, EAF-controlled blending, and Regenesis feed metering
| Document Number | CBT-PRE-TDS-003 |
| Revision | Rev 1 — April 2026 |
| OER Classification | Class 2 (±15%) OEM Engineering Release — equivalent to "FEED / DOE FEL-3" [external regulatory reference — DOE LPO / AACE 18R-97 only] |
| Status | WORKING DOCUMENT — Pre-Release Engineering Development |
| Owner | Carbotura Inc. — Engineering |
| Quality Standard | ISO 9001:2015 |
| Authorized Strategic Integrator (ASI) | Role open to qualified ASI candidates per CBT-ASI-QUAL-001 |
| RevCon Performance Baseline | RevCon 3 — $150M–$325M/yr revenue floor, 400 TPD baseline factory |
| Chairman | Allen Witters |
| Rev | Date | Author | Description |
|---|---|---|---|
| 0 | April 2026 | Carbotura Engineering | Initial Issue — Class 4 Preliminary (±30%). ICD table absent from Section 9. |
| 1 | April 2026 | Lead Systems Architect / OEM Engineering Director | Class 2 OER Upgrade. Full ICD register established per CBT-PRE-ICD-001 Rev 1 (7 ICDs, all DEFINED). Skid-Integrated Spring Isolation specification added for SHRD-SHR-001/002 and SHRD-HMR-001/002. ASI terminology applied throughout. Terminology Firewall v1.0 enforced. RevCon 3 baseline confirmed. |
- Executive Summary
- Facility Context & Module Boundaries
- Process Description
- Feedstock Design Envelope
- Canonical EAF Definition
- Module Equipment Specifications
- APS Interface Register
- Ash Supply & Logistics Basis
- Modular Installability & Interface Control (ICD Table)
- Utilities Register & Energy Balance
- Vendor Matrix
- CAPEX Estimate
- TRL / ERL / IRL Assessment
- Confidence Factor
- Availability Model
- Dust Hazard Analysis & Area Classification
- Risk Register
- Warranty Register
1. Executive Summary
Lift Conveyor Discharge
SHRD-TPS-001/002
SHRD-SHR-001/002 · 380 kW · Spring ISO
Bulk Ferrous → FCB-001/002 · −18 TPD
SHRD-HMR-001/002 · P80 ≤25 mm · Spring ISO
Fine Wire → FCB-003/004 · −7 TPD
Stream A: WTE Ash · Stream B: Recyclotron Solid Phase OmniCrude™
SHRD-APZ-001/002 · P80 <500 µm · ATEX Z21
SHRD-LWF-001–004 · ±0.5% accuracy
SHRD-MXR-001/002 · EAF = 0.25 · CV <5%
SHRD-RFB-001/002
~409 TPD blended · EAF confirmed
This TDS defines the engineering basis for the Carbotura Pregenesis Protocol Shredder Train, covering Modules 1 through 4: Primary Shredding, Hammermill size reduction, Ash Pulverizer (VRM), and Rotational Mixer blending system. The Shredder Train processes up to 1,000 TPD of Manufacturing Feedstock (MSW) blended with WTE bottom ash and/or Regenesis recirculated solids at a design Enhancement Admix-to-Feed Ratio (EAF) of 0.25. The blended material is size-reduced to P80 <25 mm and homogenized before entering the downstream Regenesis MCR Reactor.
The module operates as two parallel process paths converging at the Rotational Mixer: the main Manufacturing Feedstock path (size reduction and two-stage ferrous separation) and the optional Enhancement Admix path (pulverizing, storage, and precision metering). Combined two-stage ferrous removal achieves ≥99% efficiency for ferrous items ≥10 mm, protecting downstream equipment and ensuring a clean OmniCrude™ feed stream.
Rev 1 upgrades this document from Class 4 Preliminary to Class 2 OEM Engineering Release. The full ICD register for Modules 1–4 is established herein for the first time (7 ICDs, all DEFINED). Skid-Integrated Spring Isolation is specified for SHRD-SHR-001/002 and SHRD-HMR-001/002, eliminating all isolated slab section requirements. The Authorized Strategic Integrator (ASI) role replaces all vendor-specific integrator references, maintaining multi-ASI qualification flexibility.
2. Facility Context & Module Boundaries
2.1 Module Position in Facility
| Boundary | Definition |
|---|---|
| Upstream Boundary | Trough 1 lift conveyor discharge — point at which shredded Manufacturing Feedstock is received from Module 0B (CBT-PRE-TDS-002) |
| Downstream Boundary | Regenesis Feed Metering Bin (SHRD-RFB) discharge — point of handoff to the Regenesis Protocol |
| Exclusions | Building structure, APS external ductwork, explosion vent civil routing, fire suppression water deluge, Owner's Engineer scope |
3. Process Description
3.1 Narrative Overview
The Pregenesis Shredder Train receives Manufacturing Feedstock discharged from Trough 1 via lift conveyor and sized for entry into the primary shredder. The train processes material through a sequence of size reduction, ferrous recovery, optional Enhancement Admix metering stages before discharging homogenized feed to the Regenesis MCR at the design EAF of 0.25. The Trough 2 ash pulverizer path merges at the Ash Silo stage, providing pre-pulverized WTE Ash (Stream A) or Recyclotron Solid Phase OmniCrude™ (Stream B — raw CRB-001, pre-refining) when Enhancement Admix is active. The Recyclotron operates at Baseline MCR Mode (EAF = 0.00) without admix — Enhancement Admix is optional.
3.2 Process Flow
Manufacturing Feedstock enters at the Tire Pre-Shredder (SHRD-TPS-001/002), which conditions oversized tire bales to <500 mm for primary shredder entry. The Primary Shredder (SHRD-SHR-001/002) reduces material to P80 <150 mm. Stage 1 Magnetic Ferrous Separator (SHRD-MFS-001/002) removes bulk ferrous. Hammermill (SHRD-HMR-001/002) further reduces to P80 <25 mm. Stage 2 MFS (SHRD-MFS-003/004) removes fine wire. Size-reduced material (335 TPD at design) transfers to the Rotational Mixer. Enhancement Admix (0–84 TPD at design EAF 0.25, or zero in Baseline MCR Mode) from Ash Silos ASL-001/002 via Loss-in-Weight Feeders enters the mixer concurrently when Enhancement Mode is active. Blended output at EAF 0.25 (CV <5%) discharges to the Regenesis Feed Metering Bin.
3.3 Mass Balance (EAF = 0.25 Design Point)
| Stream | Description | Rate (TPD as-received) | Notes |
|---|---|---|---|
| Manufacturing Feedstock In | MSW received from Trough 1 / Module 0B | 1,000 | Design basis |
| Ash In — Stream A | WTE bottom ash, external supply | ~175 | At EAF=0.25; Stream B provides balance |
| Ash In — Stream B | Recyclotron Solid Phase OmniCrude™ — raw CRB-001 pre-refining, internal recycle | ~75 | 80–120 TPD range |
| Total Ash In | Combined at EAF=0.25 | 250 | = 1,000 × 0.25 |
| Ferrous Removed — Stage 1 | Post-primary shredder, MFS-001/002 | ~28–40 | 2.8–4.0% of Manufacturing Feedstock (P50) |
| Ferrous Removed — Stage 2 | Post-hammermill, MFS-003/004 | ~8–10 | Residual fine fragments |
| Total Ferrous Removed | Combined two-stage extraction | ~36–50 | Co-manufactured revenue stream |
| Blended Feed to Regenesis | Homogeneous blend to SHRD-RFB | ~1,200–1,214 | 1,000 + 250 − 36 to 50 TPD ferrous |
3.4 Key Process Parameters
| Parameter | Design Value | Alarm Low | Alarm High |
|---|---|---|---|
| Primary shredder output size (P80) | 150 mm (6 in.) | — | >200 mm sustained |
| Hammermill screen aperture | 25 mm (1 in.) | — | Screen bypass detected |
| EAF setpoint (default) | 0.25 | <0.10 (process alert) | >1.0 (hard limit) |
| Ash pulverizer output | <500 µm D90 | — | >600 µm D90 |
| Blending uniformity (CV) | <5% | — | >8% (alarm) |
| Building negative pressure | –0.075 in. WC (mid-range) | <–0.05 in. WC | >–0.10 in. WC |
| EAF accuracy (SCADA) | ±0.02 of setpoint | — | Deviation >0.02 for >2 min |
4. Feedstock Design Envelope — Shredder Train
4.1 Trough 1 Input Composition
| Parameter | Design Value | Min | Max | Notes |
|---|---|---|---|---|
| MSW bulk density | 250 kg/m³ | 150 kg/m³ | 400 kg/m³ | As-received, pre-shredded |
| Tires — max piece size | 1,500 mm dia | — | Whole passenger to OTR | Pre-shredder accepts whole tires |
| Moisture content | 25% (w.b.) | 5% | 55% | NIR-confirmed at TISAB; >55% triggers T2 routing |
| LHV (as-received) | 10–14 MJ/kg | 8 MJ/kg | 20 MJ/kg | Design basis; tires elevate LHV |
| Chlorine content | <1.5% dry | — | 2.5% dry (alert) | Affects Regenesis MCR liner life |
| Ferrous content | 5–8% by weight | 1% | 15% | MFS recovery target ≥95% at ≥5 mm |
4.2 Prohibited Materials
| Material | Reason | Detection |
|---|---|---|
| Li-ion / Li-polymer batteries | Thermal runaway and fire risk in shredder | RFID manifest; operator visual; radiation detector |
| Explosive or pyrotechnic material | Detonation risk in high-shear environment | Manifest declaration; X-ray at gate (future) |
| Radioactive material | Contamination of OmniCrude™ product stream | Portal radiation monitor at TISAB |
| Bulk liquids (>50 L per load) | Leachate overload; downstream dewatering overload | Manifest; visual inspection |
| Asbestos-containing material | ACM containment — ATEX/NESHAP conflict | Manifest declaration; licensed hauler certification |
5. Enhancement Admix Protocol
5.1 MCR Operating Modes
| Mode | EAF | Admix Source | Financial Basis | Status |
|---|---|---|---|---|
| Baseline MCR Mode | 0.00 | None | RevCon baseline — all financial projections | FINANCIALLY MODELED |
| Enhanced MCR Mode | 0.05–0.35 | WTE Ash (Stream A) and/or Recyclotron Solid Phase OmniCrude™ (Stream B) | Unmodeled upside — carbon yield uplift + client admix TMC Fee | OPTIONAL ENHANCEMENT |
| Industrial Feedstock MCR Mode | OPEN — DOE Gate: recipe defined per cooperative agreement | Coal ash, coal tailings, CMM solids ± MSW | DOE Cooperative Agreement — separate financial model | DOE GRANT PENDING |
5.2 Enhancement Admix Ratio Definition
Where madmix = mass flow of Enhancement Admix (WTE Ash Stream A and/or Recyclotron Solid Phase OmniCrude™ Stream B) and mfeedstock = mass flow of MSW Manufacturing Feedstock only. The denominator is Manufacturing Feedstock mass only — NOT total blended mass. Default design EAF = 0.25 (250 TPD ash per 1,000 TPD Manufacturing Feedstock).
| EAF | Ash (TPD) | Feedstock (TPD) | Total Blend (TPD) | Ash % of Blend |
|---|---|---|---|---|
| 0.00 | 0 | 1,000 | 1,000 | 0.0% |
| 0.10 | 100 | 1,000 | 1,100 | 9.1% |
| 0.25 (Design) | 250 | 1,000 | 1,250 | 20.0% |
| 0.50 | 500 | 1,000 | 1,500 | 33.3% |
| 1.00 | 1,000 | 1,000 | 2,000 | 50.0% |
6. Module Equipment Specifications
6.1 Primary Shredder SHRD-SHR-001/002 — Including Skid-Integrated Spring Isolation
6.2 Hammermill SHRD-HMR-001/002
6.3 Ash Pulverizer — VRM SHRD-APZ-001/002
6.4 Rotational Mixer SHRD-MXR-001/002
7. APS Interface Register — Shredder Train
7.1 APS Capture Points — Shredder Train Zone
| Tag | Location | Type | Connection | Status |
|---|---|---|---|---|
| SHRD-APS-001 | Primary Shredder enclosure | Particulate + vapor | APS manifold — 12 in. flanged per ICD §4.2 | DEFINED |
| SHRD-APS-002 | Hammermill enclosure | Particulate + vapor | APS manifold — 10 in. flanged | DEFINED |
| SHRD-APS-003 | VRM Pulverizer (ATEX Zone 21) | Fine particulate — N₂ inerted | APS manifold — 8 in. flanged; N₂ purge upstream | PENDING — ICD-A01 |
| SHRD-APS-004 | Rotational Mixer enclosure | Vapor + carbon fines | APS manifold — 8 in. flanged | DEFINED |
| SHRD-APS-005 | Ferrous Collection Bin zone | Dust | APS manifold — 6 in. flanged | DEFINED |
8. Vendor Matrix — Shredder Train
8.1 Equipment OEM Supplier Shortlist
| Equipment | Tag | Preferred OEM | Alternate OEM | Selection Status |
|---|---|---|---|---|
| Tire Pre-Shredder | SHRD-TPS-001/002 | Vecoplan VVZ 2500 | Lindner Komet 2800 | SHORTLISTED |
| Primary Shredder | SHRD-SHR-001/002 | Vecoplan VEZ 2500 | Lindner Polaris 2800 | SHORTLISTED |
| Hammermill | SHRD-HMR-001/002 | Stedman Grand Slam | Metso Lindemann LIS | SHORTLISTED |
| Magnetic Separator (Stages 1&2) | SHRD-MFS-001/002/003/004 | Eriez Suspended Electromagnet | Bunting RE Cross-Belt | SHORTLISTED |
| VRM Ash Pulverizer | SHRD-APZ-001/002 | Pfeiffer MPS 2000 BC | Loesche LM 15.2 | SHORTLISTED — pending ICD-A02 |
| Rotational Mixer | SHRD-MXR-001/002 | Readco Kurimoto CP | BHS-Sonthofen DKXC | SHORTLISTED |
| Loss-in-Weight Feeders | SHRD-LWF-001 to -004 | Schenck MULTICOR K | Coperion K-Tron K2 | SHORTLISTED |
9. Modular Installability & Interface Control
9.1 Skid Interface Specifications
| Interface | ICD Reference | Connection Type | Status |
|---|---|---|---|
| Module 0B lift conveyor → SHRD upstream handoff | ICD-SHRD-UP-001 | Flanged AR400 chute + E-stop SIL 1 + Modbus TCP feed rate | DEFINED — Rev 1 |
| Facility 32 MW PowerBlock → SHRD MCC | ICD-SHRD-PWR-001 | ASI-PBK-QC-4160-32MW + ASI-PWR-480-3PH-60A per skid | DEFINED — Rev 1 |
| Shredder Train SCADA → Facility SCADA Master | ICD-SHRD-DAT-001 | Modbus TCP/IP — ASI-DAT-MOD-TCP-M12 per skid | DEFINED — Rev 1 |
| All 9 APS capture points → APS Common Header | ICD-SHRD-APS-001 | 9× ASI-APS-FLG + N₂ supply flange + Modbus TCP VAV control | DEFINED — Rev 1 |
| WTE Ash Stream A trucks → SHRD-EAS silos | ICD-SHRD-ASH-001 | ASI-RFH-FLG-4IN-RF150 silo nozzles + pneumatic transfer | DEFINED — Rev 1 |
| SHRD-RFB → Regenesis Protocol MCR | ICD-SHRD-DN-001 | ASI-RFH-FLG-8IN-RF150 + ASI-DAT-MOD-TCP-M12 metering rate | DEFINED — Rev 1 |
| Facility PSA N₂ Generator → SHRD inerting system | ICD-SHRD-N2-001 | ASI-RFH-FLG-4IN-RF150 + Modbus TCP low-flow interlock SIL 1 | DEFINED — Rev 1 |
10. Utilities Register & Energy Balance
10.1 Electrical Load Schedule
AC Utility Bus — Frequency Specification
| Deployment Region | AC Bus Frequency | Plug Standard | Voltage | Set At |
|---|---|---|---|---|
| USA | 60Hz | NEMA 5-15 / 5-20 | 120V single-phase / 208V 3-phase | Commissioning — firmware parameter |
| Europe / UK | 50Hz | CEE 7/4 (Schuko) / BS 1363 | 230V single-phase / 400V 3-phase | Commissioning — firmware parameter |
| Asia / Pacific | 50Hz | IEC 60083 regional variants | 220–240V single-phase | Commissioning — firmware parameter |
| Middle East / Africa | 50Hz | BS 546 / regional variants | 220–240V single-phase | Commissioning — firmware parameter |
| All large motors (VFD-driven) | Frequency-agnostic | N/A — direct HVDC or VFD output | Per VFD output spec | No setting required |
| Equipment | Tag | Units Active | P50 kW | P90 (Peak) kW |
|---|---|---|---|---|
| Tire Pre-Shredder | TPS-001 | 1 | 175 | 235 |
| Primary Shredder | SHR-001/002 | 1+1 | 290 | 380 |
| Shredder HPU | SHR-HPU-001 | 1 | 30 | 45 |
| Mag. Sep. — Post-Shredder | MFS-001/002 | 1+1 | 5 | 7 |
| Hammermill | HMR-001/002 | 1+1 | 265 | 330 |
| Ash Pulverizer VRM | APZ-001/002 | 1+1 | 185 | 235 |
| Rotational Mixer | MXR-001 | 1 | 115 | 155 |
| Loss-in-weight feeders | LIW-001/002 | 2 | 15 | 22 |
| Mag. Sep. — Post-Hammermill | MFS-003/004 | 1+1 | 5 | 7 |
| Conveyors (all) | CV-xxx | — | 87 | 112 |
| Instruments / Controls | — | — | 15 | 20 |
| SUBTOTAL CORE | — | — | ~1,185 | ~1,546 |
11. Testing and Acceptance Criteria
11.1 Factory Acceptance Test (FAT)
| Test | Acceptance Criterion | Method | Status |
|---|---|---|---|
| Primary shredder throughput | ≥40 TPH sustained over 2-hour run | Belt scale on outfeed conveyor | PENDING |
| Hammermill P80 | P80 ≤25 mm on grab sample | Sieve analysis | PENDING |
| EAF blend uniformity | CV <5% on 3 consecutive 15-min grab samples | Lab analysis per ASTM E1131 | PENDING |
| Stage 1 ferrous recovery | ≥95% ferrous by weight removed at ≥10 mm | FCB weight vs. input ferrous estimate | PENDING |
| VRM product fineness | D90 <500 µm | Laser diffraction particle analysis | PENDING — requires ICD-A02 grindability test |
| Spring isolation vibration | Floor vibration ≤0.5 mm/s RMS at 2 m from skid | Vibration meter per ISO 10816 | PENDING |
11.2 Site Acceptance Test (SAT)
SAT to be defined by Carbotura Engineering following FAT completion. Minimum SAT scope: 72-hour continuous run at ≥85% design throughput, SCADA historian validation, spring isolation verification under operating load, and EAF closed-loop control response test.
12. CAPEX Estimate
12.1 Module CAPEX Summary — Class 2 ±15%
| Item | Low ($M) | High ($M) | Basis |
|---|---|---|---|
| Primary Shredders (2×) incl. Spring Isolation | 1.8 | 3.2 | Budget quotes — Vecoplan, Lindner, SSI; spring isolation per ASI (Authorized Strategic Integrator) isolation spec |
| Hammermills (2×) incl. Spring Isolation | 1.2 | 2.4 | Budget quotes — Stedman, Metso; spring isolation per ASI (Authorized Strategic Integrator) isolation spec |
| VRM Ash Pulverizers (2×) | 2.0 | 3.8 | Budget quotes — Pfeiffer MPS, Loesche LM; pending grindability test confirmation |
| Rotational Mixer (1×) | 0.6 | 1.2 | Budget quotes — Readco, BHS-Sonthofen |
| Tire Pre-Shredder (1×) | 0.5 | 0.9 | Budget quote |
| Magnetic Ferrous Separators (4×) | 0.15 | 0.38 | Budget quotes — Eriez, Bunting |
| Feeders, Conveyors, Silos | 1.0 | 1.8 | Parametric estimate |
| Electrical (MCC, cabling) | 0.8 | 1.5 | Factor estimate — 15% of equipment |
| SCADA / Controls | 0.5 | 1.0 | Factor estimate |
| Modular Assembly & erection | 1.2 | 2.2 | Factor estimate — 20% of equipment |
| Commissioning & startup | 0.3 | 0.6 | OEM supervision rates |
| First fill spares | 0.3 | 0.5 | 5% of equipment |
| Contingency (15%) | — | 0.6 | Applied to total per AACE Class 2 |
| TOTAL TDS-003 CAPEX | $10.4M | $20.1M | Class 2 ±15% | AACE 18R-97 | 2026 USD |
13. TRL / ERL / IRL Assessment
13.1 Technology and Engineering Readiness
| Module | TRL | ERL | IRL | Notes |
|---|---|---|---|---|
| Primary Shredder | 9 | 8 | 8 | Fully commercial; multiple OEM references (Vecoplan, Lindner operating records) |
| Hammermill | 9 | 8 | 8 | Fully commercial; MSW-proven (Stedman, Metso operating data) |
| VRM Ash Pulverizer (WTE ash / Enhancement Admix) | 9 | 8 | 8 | Commercial for minerals; MSW ash application requires grindability confirmation (Open Action ICD-A02) |
| Rotational Mixer (all MCR modes) | 9 | 8 | 8 | Commercial for bulk blending; IRL upgraded Rev 1 with full ICD definition |
| Tire Pre-Shredder | 9 | 8 | 8 | Fully commercial; tire recycling industry heritage |
| Magnetic Ferrous Separators (4×) | 9 | 8 | 8 | Mature commercial technology; Eriez/Bunting OEM data |
| Enhancement Admix blending integration (optional, EAF 0.05–0.35) | 7 | 6 | 6 | Ratio blending with gravimetric feeders into continuous mixer proven in cement, food, and chemical industries. Carbotura ACM-specific feedstock not yet commissioned at scale — TRL 7. Corrected from Rev 0 assessment of TRL 5–6. Baseline MCR Mode (EAF = 0.00) operates fully without this integration — TRL 9. |
| Enhancement Admix Equipment (SHRD-EAS, SHRD-APZ, SHRD-LWF) — Optional Enhancement Equipment | 9 | 5 | 5 | All individual components TRL 9. Not on critical path for Baseline MCR. Enables Enhancement Mode and DOE Industrial Feedstock MCR Mode. |
| Integrated System — Baseline MCR Mode | 8 | 7 | 8 | Individual equipment TRL 9. Baseline MCR Mode (no admix) is TRL 9 via MSW shredding/sizing heritage. Enhancement Admix integration TRL 7 (optional — not critical path). Overall system TRL 8: all required equipment proven; optional enhancement subsystem at TRL 7 does not constrain Baseline MCR commercial readiness. |
14. Confidence Factor
| Dimension | Score | Max | Basis |
|---|---|---|---|
| Equipment selection maturity | 9 | 10 | Budget quotes from 3+ OEMs per category |
| Process design basis | 9 | 10 | EAF canonical definition; feedstock envelope complete |
| Energy balance closure | 9 | 10 | Full parasitic loads included in Section 10 |
| Integration readiness (ICD) | 9 | 10 | Full ICD register established Rev 1; IRL upgraded to 8 |
| Availability / reliability | 7 | 10 | Model complete; industry benchmarks cited |
| Safety / DHA | 7 | 10 | Preliminary DHA; formal NFPA 652 DHA pending (Open Action ICD-A04) |
| Environmental (APS) | 8 | 10 | Preliminary design complete; all capture points defined |
| Cost estimate maturity | 8 | 10 | Class 2 ±15% achieved |
| TOTAL | 66/80 | 80 | Confidence Factor: 82.5% — Good / Investor-bankable |
15. Availability Model
15.1 Equipment Availability and Redundancy
| Equipment | MA | MTBF (hr) | MTTR (hr) | Redundancy |
|---|---|---|---|---|
| Primary Shredder (SHRD-SHR-001/002) | 88–92% | 720–1,200 | 4–8 | N+1 — one shredder can hold production at 60% rate while other is down |
| Hammermill (SHRD-HMR-001/002) | 90–93% | 1,000–2,000 | 3–6 | N+1 — screen/hammer change on one while other runs |
| MFS Stage 1 & 2 (SHRD-MFS-001–004) | >98% | >8,000 | <1 | 2 per stage — independent operation |
| VRM Pulverizer (SHRD-APZ-001/002) | 88–92% | 1,200–2,000 | 4–8 | N+1 — second VRM maintains ash pulverizing at reduced rate |
| Rotational Mixer (SHRD-MXR-001/002) | >95% | >4,000 | 2–4 | N+1 — paddle replacement is routine maintenance |
| Loss-in-Weight Feeders (SHRD-LWF-001–004) | >97% | >5,000 | 1–2 | 4 units — 3 required for design flow; 1 spare capacity |
| System roll-up (all modules) | ≥85% | — | — | Series/parallel combination; constraint is primary shredder |
16. Warranty Register
16.1 OEM Warranty Terms — Shredder Train
| Equipment | Tag | OEM | Warranty Period | Performance Guarantee | Status |
|---|---|---|---|---|---|
| Primary Shredder | SHRD-SHR-001/002 | Vecoplan AG | 24 months from FAT | Throughput ≥40 TPH; uptime ≥90% in 12-month period | PENDING — purchase order |
| Hammermill | SHRD-HMR-001/002 | Stedman Machine | 12 months from FAT | P80 ≤25 mm at design throughput | PENDING |
| VRM Pulverizer | SHRD-APZ-001/002 | Pfeiffer MPS | 24 months from FAT | D90 ≤500 µm at design throughput — conditional on grindability test | PENDING — ICD-A02 |
| Rotational Mixer | SHRD-MXR-001/002 | Readco Kurimoto | 18 months from FAT | CV <5% blend uniformity | PENDING |
| Loss-in-Weight Feeders | SHRD-LWF-001–004 | Schenck Process | 18 months from FAT | ±0.5% gravimetric accuracy | PENDING |
All warranty terms above are indicative based on OEM standard terms. Final warranty terms will be negotiated by the Authorized Strategic Integrator (ASI) and governed by the Unitized Warranty Passport (UWP). The UWP is the controlling warranty document and supersedes individual OEM warranty statements.
17. Risk Register
17.1 Module Risk Register
| Risk ID | Category | Severity | Mitigation |
|---|---|---|---|
| R-01 | VRM grindability test pending — APZ specification uncertain | MEDIUM | Open Action ICD-A02: OEM grindability test ($15K–$25K) required before APZ procurement release. Pfeiffer and Loesche test capability available. Results expected within 4–6 weeks of test authorization. |
| R-02 | Primary shredder lead time at 26–32 weeks — schedule critical | MEDIUM | Early procurement authorization. Parallel competitive bids from Vecoplan, Lindner, SSI. ICD-SHRD-UP-001 finalization prior to fabrication release. |
| R-03 | Combustible dust hazard at APZ / SHRD-EAS zones — safety / regulatory | HIGH | Preliminary DHA completed; formal NFPA 652 DHA in progress (Open Action ICD-A04). Z-03/Z-04 zones N₂-inerted per ICD-SHRD-N2-001. Combustible dust classification drives ATEX-rated enclosures for all APZ equipment. |
| R-04 | Li-battery in Manufacturing Feedstock — fire / thermal runaway in shredder | HIGH | Thermal camera screening at TISAB approach (upstream — Module 0A). Quarantine bay protocol. CO monitoring trigger at primary shredder. Water deluge at QA-01 bay. NFPA fire suppression throughout building. |
| R-05 | EAF accuracy deviation — OmniCrude™ yield impact | MEDIUM | Dedicated belt scale on feedstock path. Loss-in-weight feeders with ±0.5% accuracy. SCADA EAF alarm at ±0.02 deviation for >2 minutes. RevCon warranty clause triggered at EAF deviation ≥0.05. |
RevCon 3 Performance Baseline | Authorized Strategic Integrator (ASI) Integration Model | Class 2 OER ±15%