Carbotura
Engineering Portal
Confidential
Pregenesis Protocol — Technical Design Specification

Modules 1–4: Primary Shredding, Hammermill,
Ash Pulverizer & Rotational Mixer

Pregenesis Shredder Train — complete size reduction, ferrous separation, AFR-controlled blending, and Regenesis feed metering

Doc No.CBT-PRE-TDS-003
RevisionRev 1
OER ClassClass 2 ±15%
DateApril 2026
ClassificationConfidential
RevCon BaselineRevCon 3
Document Control
Document NumberCBT-PRE-TDS-003
RevisionRev 1 — April 2026
OER ClassificationClass 2 (±15%) OEM Engineering Release — equivalent to "FEED / DOE FEL-3" [external regulatory reference — DOE LPO / AACE 18R-97 only]
StatusIssued for Review — PE Sign-Off / Investor Bill of Sale
OwnerCarbotura Inc. — Engineering
Quality StandardISO 9001:2015
Authorized Strategic Integrator (ASI)Role open to qualified ASI candidates per CBT-ASI-QUAL-001
RevCon Performance BaselineRevCon 3 — $150M–$325M/yr revenue floor, 400 TPD baseline factory
ChairmanAllen Witters
Revision History
RevDateAuthorDescription
0April 2026Carbotura EngineeringInitial Issue — Class 4 Preliminary (±30%). ICD table absent from Section 9.
1April 2026Lead Systems Architect / OEM Engineering DirectorClass 2 OER Upgrade. Full ICD register established per CBT-PRE-ICD-001 Rev 1 (7 ICDs, all DEFINED). Skid-Integrated Spring Isolation specification added for SHRD-SHR-001/002 and SHRD-HMR-001/002. ASI terminology applied throughout. Terminology Firewall v1.0 enforced. RevCon 3 baseline confirmed.

1. Executive Summary

DIAG-SHRD-001 Shredder Train — Process Flow & Equipment Sequence
Process Flow
Feed Input
Trough 1
Lift Conveyor Discharge
Size Reduction
Tire Pre-Shredder
SHRD-TPS-001/002
Primary Shredder
SHRD-SHR-001/002 · 380 kW · Spring ISO
MFS Stage 1
Bulk Ferrous → FCB-001/002 · −18 TPD
Hammermill
SHRD-HMR-001/002 · P80 ≤25 mm · Spring ISO
MFS Stage 2
Fine Wire → FCB-003/004 · −7 TPD
Susceptor Preparation
Ash Silos ASL-001/002
Stream A WTE · Stream B Recycle
VRM Pulverizer
SHRD-APZ-001/002 · P80 <500 µm · ATEX Z21
Loss-in-Weight Feeders
SHRD-LWF-001–004 · ±0.5% accuracy
Blending and Metering
Rotational Mixer
SHRD-MXR-001/002 · AFR = 0.25 · CV <5%
Regenesis Feed Bin
SHRD-RFB-001/002
To Regenesis MCR
~409 TPD blended · AFR confirmed
Shredder Train sequence from Trough 1 discharge to Regenesis Feed Metering Bin. N+1 redundancy applies to Primary Shredder, Hammermill, and VRM Pulverizer. APS Capture Stream runs parallel to all enclosed zones (not shown).
DIAG-SHRD-002 Trough 2 NIR Moisture Routing — Decision Logic
Decision Tree
NIR Moisture Sensor — Trough 2 Discharge Conveyor
SCADA Routes Material Based on NIR Reading + Material Type
ASH PATH
Moisture below 15% — Bypass Dryer
Moisture 15 to 30% — Dryer Trim Cycle
Moisture above 30% — Full Dryer Cycle
Lumpbreaker / Cage Mill
VRM Pulverizer — P80 below 500um
Ash Silo ASL-001
SLUDGE PATH
Moisture below 15% — FLAG ANOMALOUS — Supervisor Review
Moisture 15 to 60% — Pre-Dewatering
Moisture above 60% — Pre-Dewatering MANDATORY
Paddle Dryer — 130 to 160 deg C
Impact / Pin Mill Pulverizer
Sludge Silo ASL-002
Both silos — Pneumatic transfer to Shredder Train — Rotational Mixer at AFR 0.25
SCADA executes this routing logic automatically on NIR reading. Manifest-declared material type supplements the NIR reading. Operator may override any gate position from HMI at any time. All routing decisions logged with timestamp for audit trail.
Document Boundary Statement
This Technical Design Specification defines module-level technical requirements, interfaces, testing, and warranty boundaries only; commercial risk allocation, financing structures, delivery arrangements, and lender requirements are addressed in separate contractual and financing documents.
Manufacturing Classification Statement
This Technical Design Specification describes module-level requirements for an Advanced Circular Manufacturing subsystem and does not define or imply waste treatment, storage, or disposal activities.
Near-Zero Design Intent
The Pregenesis Shredder Train is engineered as a closed-loop manufacturing subsystem designed for near-zero emissions, near-zero discharge, and near-zero residual. All process enclosures operate under continuous negative pressure. There is no routine atmospheric discharge from any module in this group. The APS recovers all airborne particulates and vapors as product streams via continuous negative-pressure capture.

This TDS defines the engineering basis for the Carbotura Pregenesis Protocol Shredder Train, covering Modules 1 through 4: Primary Shredding, Hammermill size reduction, Ash Pulverizer (VRM), and Rotational Mixer blending system. The Shredder Train processes up to 1,000 TPD of Manufacturing Feedstock (MSW) blended with WTE bottom ash and/or Regenesis recirculated solids at a design Ash-to-Feedstock Ratio (AFR) of 0.25. The blended material is size-reduced to P80 <25 mm and homogenized before entering the downstream Regenesis MCR Reactor.

The module operates as two parallel process paths converging at the Rotational Mixer: the main Manufacturing Feedstock path (size reduction and two-stage ferrous separation) and the ash susceptor path (pulverizing, storage, and precision metering). Combined two-stage ferrous removal achieves ≥99% efficiency for ferrous items ≥10 mm, protecting downstream equipment and ensuring a clean OmniCrude™ feed stream.

Rev 1 upgrades this document from Class 4 Preliminary to Class 2 OEM Engineering Release. The full ICD register for Modules 1–4 is established herein for the first time (7 ICDs, all DEFINED). Skid-Integrated Spring Isolation is specified for SHRD-SHR-001/002 and SHRD-HMR-001/002, eliminating all isolated slab section requirements. The Authorized Strategic Integrator (ASI) role replaces all vendor-specific integrator references, maintaining multi-ASI qualification flexibility.

2. Facility Context & Module Boundaries

BoundaryDefinition
Upstream BoundaryTrough 1 lift conveyor discharge — point at which shredded Manufacturing Feedstock is received from Module 0B (CBT-PRE-TDS-002)
Downstream BoundaryRegenesis Feed Metering Bin (SHRD-RFB) discharge — point of handoff to the Regenesis Protocol
ExclusionsBuilding structure, APS external ductwork, explosion vent civil routing, fire suppression water deluge, Owner's Engineer scope

3. Process Description

3.3 Mass Balance (AFR = 0.25 Design Point)

StreamDescriptionRate (TPD as-received)Notes
Manufacturing Feedstock InMSW received from Trough 1 / Module 0B1,000Design basis
Ash In — Stream AWTE bottom ash, external supply~175At AFR=0.25; Stream B provides balance
Ash In — Stream BRegenesis solids recycle, internal~7580–120 TPD range
Total Ash InCombined at AFR=0.25250= 1,000 × 0.25
Ferrous Removed — Stage 1Post-primary shredder, MFS-001/002~28–402.8–4.0% of Manufacturing Feedstock (P50)
Ferrous Removed — Stage 2Post-hammermill, MFS-003/004~8–10Residual fine fragments
Total Ferrous RemovedCombined two-stage extraction~36–50Co-manufactured revenue stream
Blended Feed to RegenesisHomogeneous blend to SHRD-RFB~1,200–1,2141,000 + 250 − 36 to 50 TPD ferrous

3.4 Key Process Parameters

ParameterDesign ValueAlarm LowAlarm High
Primary shredder output size (P80)150 mm (6 in.)>200 mm sustained
Hammermill screen aperture25 mm (1 in.)Screen bypass detected
AFR setpoint (default)0.25<0.10 (process alert)>1.0 (hard limit)
Ash pulverizer output<500 µm D90>600 µm D90
Blending uniformity (CV)<5%>8% (alarm)
Building negative pressure–0.075 in. WC (mid-range)<–0.05 in. WC>–0.10 in. WC
AFR accuracy (SCADA)±0.02 of setpointDeviation >0.02 for >2 min

5. Canonical AFR Definition

AFR Canonical Definition — Applied to All Carbotura Technical Documents and SCADA Control Logic
AFR = mash / mfeedstock
Where mash = mass flow of ash (WTE + Regenesis solids) and mfeedstock = mass flow of MSW Manufacturing Feedstock only. The denominator is Manufacturing Feedstock mass only — NOT total blended mass. Default design AFR = 0.25 (250 TPD ash per 1,000 TPD Manufacturing Feedstock).
AFRAsh (TPD)Feedstock (TPD)Total Blend (TPD)Ash % of Blend
0.0001,0001,0000.0%
0.101001,0001,1009.1%
0.25 (Design)2501,0001,25020.0%
0.505001,0001,50033.3%
1.001,0001,0002,00050.0%

6. Module Equipment Specifications

6.1 Primary Shredder SHRD-SHR-001/002 — Including Skid-Integrated Spring Isolation

Skid-Integrated Spring Isolation Mandate — CED-MECH-003
SHRD-SHR-001/002 incorporates a factory-poured inertia base and kinetic spring isolation mounts within the skid boundary per ASI-ISO-SHRD-SHR-001/002. No isolated slab sections, embedded spring rails, or field-poured inertia blocks are required or permitted at the site. Standard facility slab per DUMP-BLD-001 is the complete civil interface. Full specification in CBT-PRE-ICD-001 Rev 1 Section 5 →
Primary Shredder SHRD-SHR-001/002
Cutter Gap
150 mm
Hook Geometry
Aggressive hook, 8-hook rotor configuration
Nominal Output P80
150 mm (6 in.) — empirical OEM basis
Throughput per Unit
40–60 TPH (MSW, as-received)
Drive
Hydraulic, variable speed
Motor
290 kW P50, 380 kW peak
Redundancy
2× units — 1 operating + 1 standby/parallel — 50% duty cycle
Spring Isolation System
ASI-ISO-SHRD-SHR-001/002 — 3.0 in. static deflection; fn 0.85–0.95 Hz; ≥93% isolation efficiency at 2 Hz; 8× Kinetics SLF mounts per unit; factory-poured inertia base 28,000–34,000 lb within skid frame
APS Connection
Sealed Hardox enclosure, negative-pressure extraction port
APS CFM Normal / Peak
1,200 / 2,000 CFM — process-capture basis only

6.2 Hammermill SHRD-HMR-001/002

Hammermill SHRD-HMR-001/002
Output Target
P95 ≤ 25 mm (1 in. screen aperture)
Grizzly Opening
50 × 50 mm
Design Recirculation
5% of feed rate; alarm at >5% sustained for >10 min
Throughput per Unit
40–55 TPH
Motor
265 kW P50, 330 kW peak
Redundancy
2× units — 1 operating + 1 standby — 50% duty cycle
Spring Isolation
ASI-ISO-SHRD-HMR-001/002 — 2.0 in. deflection; fn ~1.1 Hz; ≥98% isolation at 15 Hz; 6× mounts per unit; factory-poured inertia base 22,000–26,000 lb
APS CFM Normal / Peak
1,500 / 2,500 CFM — process-capture basis only

6.3 Ash Pulverizer — VRM SHRD-APZ-001/002

Ash Pulverizer (Vertical Roller Mill) SHRD-APZ-001/002
Technology
Vertical Roller Mill (VRM) — Pfeiffer MPS or Loesche LM series
Output Specification
<500 µm D90
Specific Energy
15–22 kWh/t (WTE ash); 18–28 kWh/t (Regenesis char) — [Calculated — basis: Pfeiffer/Loesche OEM grindability test data; confirmation required per Open Action ICD-A02]
Motor
185 kW P50, 235 kW peak
N₂ Inerting
Zone Z-03 — 99.9% N₂ at 7 bar; 60 Nm³/hr normal via ASI-OCB-FLG-4IN-RF150
APS CFM Normal / Peak
800 / 1,400 CFM — ATEX-rated sealed enclosure; combustible dust classification
Condition Precedent
OEM grindability test required pre-procurement ($15K–$25K). Must complete before final VRM equipment order. Open Action ICD-A02.

6.4 Rotational Mixer SHRD-MXR-001/002

Rotational Mixer SHRD-MXR-001/002
Type
Rotational / paddle mixer, continuous
Blending Target
CV <5% (Coefficient of Variation of blend uniformity)
Throughput
Up to 60 TPH blended feed per unit
Motor
115 kW P50, 155 kW peak
APS CFM Normal / Peak
600 / 1,000 CFM — drum end seal extraction ports

9. Modular Installability & Interface Control

ICD Rev 1 — Full Register Established
The complete ICD register for Modules 1–4 is published herein for the first time. All 7 ICDs are DEFINED. Interface Readiness Level upgraded from IRL 5–6 (Rev 0 conceptual) to IRL 8 (Rev 1 FEED-validated). See full specification: CBT-PRE-ICD-001 Rev 1 →
InterfaceICD ReferenceConnection TypeStatus
Module 0B lift conveyor → SHRD upstream handoffICD-SHRD-UP-001Flanged AR400 chute + E-stop SIL 1 + Modbus TCP feed rateDEFINED — Rev 1
Facility 32 MW PowerBlock → SHRD MCCICD-SHRD-PWR-001ASI-PBK-QC-4160-32MW + ASI-PWR-480-3PH-60A per skidDEFINED — Rev 1
Shredder Train SCADA → Facility SCADA MasterICD-SHRD-DAT-001Modbus TCP/IP — ASI-DAT-MOD-TCP-M12 per skidDEFINED — Rev 1
All 9 APS capture points → APS Common HeaderICD-SHRD-APS-0019× ASI-APS-FLG + N₂ supply flange + Modbus TCP VAV controlDEFINED — Rev 1
WTE Ash Stream A trucks → SHRD-ASL silosICD-SHRD-ASH-001ASI-OCB-FLG-4IN-RF150 silo nozzles + pneumatic transferDEFINED — Rev 1
SHRD-RFB → Regenesis Protocol MCRICD-SHRD-DN-001ASI-OCB-FLG-8IN-RF150 + ASI-DAT-MOD-TCP-M12 metering rateDEFINED — Rev 1
Facility PSA N₂ Generator → SHRD inerting systemICD-SHRD-N2-001ASI-OCB-FLG-4IN-RF150 + Modbus TCP low-flow interlock SIL 1DEFINED — Rev 1

10. Utilities Register & Energy Balance

10.1 Electrical Load Schedule

EquipmentTagUnits ActiveP50 kWP90 (Peak) kW
Tire Pre-ShredderTPS-0011175235
Primary ShredderSHR-001/0021+1290380
Shredder HPUSHR-HPU-00113045
Mag. Sep. — Post-ShredderMFS-001/0021+157
HammermillHMR-001/0021+1265330
Ash Pulverizer VRMAPZ-001/0021+1185235
Rotational MixerMXR-0011115155
Loss-in-weight feedersLIW-001/00221522
Mag. Sep. — Post-HammermillMFS-003/0041+157
Conveyors (all)CV-xxx87112
Instruments / Controls1520
SUBTOTAL CORE~1,185~1,546

12. CAPEX Estimate

AACE Classification — Class 2 (±15%) | 2026 USD
Upgraded from Class 4 ±30% (Rev 0) to Class 2 ±15% (Rev 1). Estimating methodology: factored/parametric — equipment costs from budget quotes (3+ OEMs per category), ROM quotes, and published industry benchmarks.
ItemLow ($M)High ($M)Basis
Primary Shredders (2×) incl. Spring Isolation1.83.2Budget quotes — Vecoplan, Lindner, SSI; spring isolation per ASI-ISO spec
Hammermills (2×) incl. Spring Isolation1.22.4Budget quotes — Stedman, Metso; spring isolation per ASI-ISO spec
VRM Ash Pulverizers (2×)2.03.8Budget quotes — Pfeiffer MPS, Loesche LM; pending grindability test confirmation
Rotational Mixer (1×)0.61.2Budget quotes — Readco, BHS-Sonthofen
Tire Pre-Shredder (1×)0.50.9Budget quote
Magnetic Ferrous Separators (4×)0.150.38Budget quotes — Eriez, Bunting
Feeders, Conveyors, Silos1.01.8Parametric estimate
Electrical (MCC, cabling)0.81.5Factor estimate — 15% of equipment
SCADA / Controls0.51.0Factor estimate
Modular Assembly & erection1.22.2Factor estimate — 20% of equipment
Commissioning & startup0.30.6OEM supervision rates
First fill spares0.30.55% of equipment
Contingency (15%)0.6Applied to total per AACE Class 2
TOTAL TDS-003 CAPEX$10.4M$20.1MClass 2 ±15% | AACE 18R-97 | 2026 USD

13. TRL / ERL / IRL Assessment

ModuleTRLERLIRLNotes
Primary Shredder988Fully commercial; multiple OEM references (Vecoplan, Lindner operating records)
Hammermill988Fully commercial; MSW-proven (Stedman, Metso operating data)
VRM Ash Pulverizer7–877Commercial for minerals; MSW ash application requires grindability confirmation (Open Action ICD-A02)
Rotational Mixer878Commercial for bulk blending; IRL upgraded Rev 1 with full ICD definition
Tire Pre-Shredder988Fully commercial; tire recycling industry heritage
Magnetic Ferrous Separators (4×)988Mature commercial technology; Eriez/Bunting OEM data
Integrated System778IRL upgraded from 5–6 to 8 with full ICD register definition (Rev 0→Rev 1)

14. Confidence Factor

DimensionScoreMaxBasis
Equipment selection maturity910Budget quotes from 3+ OEMs per category
Process design basis910AFR canonical definition; feedstock envelope complete
Energy balance closure910Full parasitic loads included in Section 10
Integration readiness (ICD)910Full ICD register established Rev 1; IRL upgraded to 8
Availability / reliability710Model complete; industry benchmarks cited
Safety / DHA710Preliminary DHA; formal NFPA 652 DHA pending (Open Action ICD-A04)
Environmental (APS)810Preliminary design complete; all capture points defined
Cost estimate maturity810Class 2 ±15% achieved
TOTAL66/8080Confidence Factor: 82.5% — Good / Investor-bankable

17. Risk Register

Risk IDCategorySeverityMitigation
R-01VRM grindability test pending — APZ specification uncertainMEDIUMOpen Action ICD-A02: OEM grindability test ($15K–$25K) required before APZ procurement release. Pfeiffer and Loesche test capability available. Results expected within 4–6 weeks of test authorization.
R-02Primary shredder lead time at 26–32 weeks — schedule criticalMEDIUMEarly procurement authorization. Parallel competitive bids from Vecoplan, Lindner, SSI. ICD-SHRD-UP-001 finalization prior to fabrication release.
R-03Combustible dust hazard at APZ / SHRD-ASL zones — safety / regulatoryHIGHPreliminary DHA completed; formal NFPA 652 DHA in progress (Open Action ICD-A04). Z-03/Z-04 zones N₂-inerted per ICD-SHRD-N2-001. Combustible dust classification drives ATEX-rated enclosures for all APZ equipment.
R-04Li-battery in Manufacturing Feedstock — fire / thermal runaway in shredderHIGHThermal camera screening at TISAB approach (upstream — Module 0A). Quarantine bay protocol. CO monitoring trigger at primary shredder. Water deluge at QA-01 bay. NFPA fire suppression throughout building.
R-05AFR accuracy deviation — OmniCrude™ yield impactMEDIUMDedicated belt scale on feedstock path. Loss-in-weight feeders with ±0.5% accuracy. SCADA AFR alarm at ±0.02 deviation for >2 minutes. RevCon warranty clause triggered at AFR deviation ≥0.05.
END OF DOCUMENT — CBT-PRE-TDS-003 | Rev 1 | April 2026 | CONFIDENTIAL — CARBOTURA INC. — ALL RIGHTS RESERVED
RevCon 3 Performance Baseline | Authorized Strategic Integrator (ASI) Integration Model | Class 2 OER ±15%